โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Garland Downtown Renovation

520 W. State St., Garland, TX 75040, Garland, TX, 75040
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022009796
$22.0M
Project Value
300,000
Square Feet
$73/sqft
Cost/SqFt
2y 1mo
Duration
Registered:Jan 21, 2022
Start:Dec 1, 2021
Target:Dec 23, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

The renovation of the downtown square along with 14 blocks of renovated pedestrian streetscape.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 21, 2022
Construction Start
December 1, 2021
Expected Completion
December 23, 2023