โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

RCISD - Agriculture Project Center

700 FM 2641, Royse City, TX 75189, Royse City, TX, 75189
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022020129
$7.0M
Project Value
30,500
Square Feet
$230/sqft
Cost/SqFt
1 year
Duration
Registered:May 27, 2022
Start:Aug 1, 2022
Target:Aug 1, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

1 Story AG barn and event center

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 27, 2022
Construction Start
August 1, 2022
Expected Completion
August 1, 2023