๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Pinckney Trail Connection

1700 South St, Houston, TX 77009, Houston, TX, 77009
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022023475
$650K
Project Value
924
Square Feet
$703/sqft
Cost/SqFt
3 months
Duration
Registered:Jul 11, 2022
Start:Oct 3, 2022
Target:Jan 6, 2023
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Proposed trail, retaining wall, streetlights, sanitary sewer, water line, pavement markings, signs, demolition, etc.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 11, 2022
Construction Start
October 3, 2022
Expected Completion
January 6, 2023