๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Eastland, Phase 3A
Approx. 500 ft southeast of CR 260 & FM 741, Crandall, TX 75114, Crandall, TX, 75114
Completed100%
๐Project Metrics
TDLR #TABS2023004254$102K
Project Value
6,820
Square Feet
$15/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Oct 31, 2022
Start:Mar 4, 2023
Target:Apr 1, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Project scope includes street paving, grading, storm drainage, water and sanitary sewer improvements for a single family residential development
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 31, 2022
Construction Start
March 4, 2023
Expected Completion
April 1, 2024
๐Related Projects
Property Owner
๐ค
KL LHB DSD AIV A DELAWARE LIMITED LIABILITY COMPANY
Contact: Nathan Holt
View company profile
6900 East Camelback Road Suite 800, Scottsdale, Arizona 85251
Design Firm
๐๏ธ
LJA Engineering, Inc.
4 projects ยท $80.7M
View all projects
6060 N Central Expressway Suite 400, Dallas, Texas 75206