Funding type
This project involves public funds, public land, or is a Federally funded roadway project.
Hondo Downtown Sidewalks
Avenue M, 17th Street, Avenue K, Hondo, TX, 78861
Hondo Downtown Sidewalks is a renovation/alteration project at Avenue M, 17th Street, Avenue K, Hondo, in Medina County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2023). The project has an estimated value of $285K across about 6,687 sq ft.
- Estimated project value
- $285K
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 6,687 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $43/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 6 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
4 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
21 days after the preceding date shown.
Source: TDLR filing
View source recordProject closed · TDLR filing
The project record was closed in TDLR.
184 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
Same day as the preceding date shown.
Source: TDLR filing
View source record
Project Closed
Project has been completed and closed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 78861 (Hondo)
One email per change. Unsubscribe in one click. Privacy.
Hondo Downtown Sidewalks is a Renovation/Alteration project located at Avenue M, 17th Street, Avenue K, Hondo, TX 78861 in Hondo, Texas. The project has an estimated value of $285K covering 6,687 sq ft. City of Hondo is the property owner and TRC Engineers, Inc. is the design firm of record. The project was registered with TDLR on February 28, 2023.
Frequently Asked Questions
What is Hondo Downtown Sidewalks?
Hondo Downtown Sidewalks is a renovation/alteration project at Avenue M, 17th Street, Avenue K in Hondo, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Public sidewalks and curb ramps: Ave M (east side) between 18th/17th; 17th St (south side) between Ave M/Ave K; Ave K (west side)between 17th/18th.
Is Hondo Downtown Sidewalks open in Hondo?
Construction on Hondo Downtown Sidewalks is complete — TDLR records show the project passed its required accessibility inspection in Sep 2023. The building is finished and very likely open.
Where is Hondo Downtown Sidewalks located?
Hondo Downtown Sidewalks is located at Avenue M, 17th Street, Avenue K, Hondo, TX, 78861, in Medina County.
Who is the owner or developer of Hondo Downtown Sidewalks?
City of Hondo is the property owner/developer of record for Hondo Downtown Sidewalks, per its TDLR project registration.
Who is the architect or design firm for Hondo Downtown Sidewalks?
TRC Engineers, Inc. is the design firm of record for Hondo Downtown Sidewalks, according to its TDLR filing.
How much does Hondo Downtown Sidewalks cost and how big is it?
Hondo Downtown Sidewalks has an estimated construction value of $285K and approximately 6,687 square feet (about $43/sqft), based on its TDLR filing.
Scope of Work
Public sidewalks and curb ramps: Ave M (east side) between 18th/17th; 17th St (south side) between Ave M/Ave K; Ave K (west side)between 17th/18th.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
Avenue M, 17th Street, Avenue K, Hondo, TX, 78861
Related Projects
Watch all construction in 78861 (Hondo)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Hondo?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.