๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

US 59 - CSJ: 0177-02-057

Shepherd to Cleveland, Cleveland, TX 77327, Cleveland, TX, 77327
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023014667
$150K
Project Value
19,100
Square Feet
$8/sqft
Cost/SqFt
4y 11mo
Duration
Registered:Mar 21, 2023
Start:Nov 1, 2023
Target:Sep 15, 2028
Remaining:993 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Convert highway to 4-Lane Frwy with 2-Lane NB & SB Frontage Rd (Future I-69) - includes constructing 4,072 LF of new sidewalk along SB frontage road.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 21, 2023
Construction Start
November 1, 2023
Expected Completion
September 15, 2028

Quick Actions

TDLR ID: TABS2023014667

Registered Accessibility Specialist

๐Ÿ“‹
FRANK,FONSECA
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201