Funding type
This project involves public funds, public land, or is a Federally funded roadway project.
US 59 (CSJ: 0089-07-154, etc.)
From: 1.0 MI S OF FM 961 To: SH 60, Wharton, TX, 77488
US 59 (CSJ: 0089-07-154, etc.) is a new construction project at From: 1.0 MI S OF FM 961 To: SH 60, Wharton, in Wharton County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Apr 2024 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $314K across about 30,336 sq ft.
- Estimated project value
- $314K
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 30,336 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $10/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 4 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
4 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
Same day as the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
161 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
122 days after the preceding date shown.
Source: TDLR filing
View source record
Review Complete
Design review complete, construction may proceed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 77488 (Wharton)
One email per change. Unsubscribe in one click. Privacy.
US 59 (CSJ: 0089-07-154, etc.) is a New Construction project located at From: 1.0 MI S OF FM 961 To: SH 60, Wharton, TX 77488 in Wharton, Texas. The project has an estimated value of $314K covering 30,336 sq ft. TxDOT District: Yoakum is the property owner and CivilCorp, LLC is the design firm of record. The project was registered with TDLR on June 27, 2023.
Frequently Asked Questions
What is US 59 (CSJ: 0089-07-154, etc.)?
US 59 (CSJ: 0089-07-154, etc.) is a new construction project at From: 1.0 MI S OF FM 961 To: SH 60 in Wharton, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Upgrade to Rural Freeway ( Future I-69 Corridor) Including Widen Pavement, Median Construction Realign of Roadway, Interchange Improvements, Upgrade Standards, Construct Interchange and Proposed Drainage Mortifications.
Is US 59 (CSJ: 0089-07-154, etc.) open in Wharton?
US 59 (CSJ: 0089-07-154, etc.) was scheduled to finish construction in Apr 2024 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.
Where is US 59 (CSJ: 0089-07-154, etc.) located?
US 59 (CSJ: 0089-07-154, etc.) is located at From: 1.0 MI S OF FM 961 To: SH 60, Wharton, TX, 77488, in Wharton County.
Who is the owner or developer of US 59 (CSJ: 0089-07-154, etc.)?
TxDOT District: Yoakum is the property owner/developer of record for US 59 (CSJ: 0089-07-154, etc.), per its TDLR project registration.
Who is the architect or design firm for US 59 (CSJ: 0089-07-154, etc.)?
CivilCorp, LLC is the design firm of record for US 59 (CSJ: 0089-07-154, etc.), according to its TDLR filing.
How much does US 59 (CSJ: 0089-07-154, etc.) cost and how big is it?
US 59 (CSJ: 0089-07-154, etc.) has an estimated construction value of $314K and approximately 30,336 square feet (about $10/sqft), based on its TDLR filing.
Scope of Work
Upgrade to Rural Freeway ( Future I-69 Corridor) Including Widen Pavement, Median Construction Realign of Roadway, Interchange Improvements, Upgrade Standards, Construct Interchange and Proposed Drainage Mortifications.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
From: 1.0 MI S OF FM 961 To: SH 60, Wharton, TX, 77488
Related Projects
Same Owner
$37.03B totalWatch all construction in 77488 (Wharton)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Wharton?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.