Bering Drive Mobility and Drainage Improvements
Bering Drive Mobility and Drainage Improvements is a new construction project at Bering Drive, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jan 2026). The project has an estimated value of $5.0M across about 114,460 sq ft.
๐Project Metrics
TDLR #TABS2023026604Inspection Complete
Final inspection completed, awaiting project closure
Bering Drive Mobility and Drainage Improvements is a New Construction project located at Bering Drive, Houston, TX 77057 in Houston, Texas. The project has an estimated value of $5.0M covering 114,460 sq ft. St. George Place Redevelopment Authority / TIRZ 1 is the property owner and Gauge Engineering is the design firm of record. The project was registered with TDLR on August 23, 2023.
โFrequently Asked Questions
What is Bering Drive Mobility and Drainage Improvements?
Bering Drive Mobility and Drainage Improvements is a new construction project at Bering Drive in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Fully reconstruct the roadway to convert it from an elevated asphalt roadway with roadside ditches to a curb and gutter concrete roadway with sidewalks. Improve the drainage with new upgraded storm sewer boxes.
Is Bering Drive Mobility and Drainage Improvements open in Houston?
Construction on Bering Drive Mobility and Drainage Improvements is complete โ TDLR records show the project passed its required accessibility inspection in Jan 2026. The building is finished and very likely open.
Where is Bering Drive Mobility and Drainage Improvements located?
Bering Drive Mobility and Drainage Improvements is located at Bering Drive, Houston, TX, 77057, in Harris County.
Who is the owner or developer of Bering Drive Mobility and Drainage Improvements?
St. George Place Redevelopment Authority / TIRZ 1 is the property owner/developer of record for Bering Drive Mobility and Drainage Improvements, per its TDLR project registration.
Who is the architect or design firm for Bering Drive Mobility and Drainage Improvements?
Gauge Engineering is the design firm of record for Bering Drive Mobility and Drainage Improvements, according to its TDLR filing.
How much does Bering Drive Mobility and Drainage Improvements cost and how big is it?
Bering Drive Mobility and Drainage Improvements has an estimated construction value of $5.0M and approximately 114,460 square feet (about $44/sqft), based on its TDLR filing.
๐Scope of Work
Fully reconstruct the roadway to convert it from an elevated asphalt roadway with roadside ditches to a curb and gutter concrete roadway with sidewalks. Improve the drainage with new upgraded storm sewer boxes.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐ Project Timeline
Filed
Aug 23, 2023
Review Complete
Aug 23, 2023
Inspection Complete
Jan 4, 2026
Closed
865d
Construction phase
๐Related Projects
Property Owner
Design Firm
Registered Accessibility Specialist
Harris County Economy
Explore Area
Find Professionals
Need a contractor for this project?
Browse verified general contractors active in Harris County
Find General Contractors in Harris