UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room
221 9th Street, Galveston, TX, 77555
UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room is a renovation/alteration project at 221 9th Street, Galveston, in Galveston County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $1.5M across about 360 sq ft.
- Estimated project value
- $1.5M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 360 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $4.17K/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 3 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
6 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
Same day as the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
98 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
90 days after the preceding date shown.
Source: TDLR filing
View source recordInspection complete · TDLR filing
The filing records completion of the accessibility inspection.
792 days after the preceding date shown.
Source: TDLR filing
View source recordProject closed · TDLR filing
The project record was closed in TDLR.
131 days after the preceding date shown.
Source: TDLR filing
View source record
📰About UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room
The renovation of Galveston National Laboratory Level 2 at 221 9th Street in Galveston, Texas, is complete. This project, filed under the name UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room, involved a specific alteration of the BSL-4 laboratory environment. The scope included the addition of a new fumigation room and a trench drain. The total estimated cost for this work was $1,500,000.
UTMB is the owner of record for this facility. Perkins&Will served as the design firm, guiding the architectural and engineering aspects of the renovation. Kathy S Rodriguez was the registered accessibility specialist associated with the project filings. The work was classified as a Renovation/Alteration, focusing on a 360 sq ft area of the building. This results in a cost per square foot of $4167, a figure that reflects the specialized nature of the laboratory upgrades.
The project timeline began with registration and plan review in August 2023. Construction was scheduled to start in December 2023, with a planned completion date of February 2024. The final inspection passed in May 2026. TDLR closed the project file in September 2026, which marks the end of the accessibility review process for this construction.
Context and Comparisons
This project’s estimated cost is above the county median for its type, placing it in the top quarter of Galveston County renovation filings. The scheduled build window of 90 days is close to the county median of 120 days. The cost per square foot of $4167 is significantly above the county median of $74, consistent with the high-specification requirements of a BSL-4 laboratory.
UTMB has six other TDLR-registered projects totaling $29,364,738, including the large RB6 - Research Building No. 6 project. Perkins&Will has six other TDLR-registered projects totaling $133,025,000, ranging from small renovations to major hospital developments. Nearby registered projects include The Meridian and Fairfield by Marriott, both renovation/alteration projects in the Galveston area.
Project Closed
Project has been completed and closed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 77555 (Galveston)
One email per change. Unsubscribe in one click. Privacy.
UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room is a Renovation/Alteration project located at 221 9th Street, Galveston, TX 77555 in Galveston, Texas. The project has an estimated value of $1.5M covering 360 sq ft. UTMB is the property owner and Perkins&Will is the design firm of record. The project was registered with TDLR on August 25, 2023.
Frequently Asked Questions
What work was done at Galveston National Laboratory Level 2?
The renovation included the addition of a fumigation room and a trench drain within the BSL-4 laboratory. The project was filed as a conversion of Animal Room 2.300 to a Fumigation Room.
Who is the owner and design firm for this project?
UTMB is the owner of record. Perkins&Will is the design firm of record. Kathy S Rodriguez was the registered accessibility specialist.
What is the status of the TDLR file for this project?
TDLR closed the project file in September 2026. The final inspection passed in May 2026, marking the end of the accessibility review process.
How much did this renovation cost?
The estimated cost was $1,500,000. This is above the Galveston County median for renovation/alteration projects, which is $250,000.
Is the business open?
The TDLR record indicates the construction project is closed. It does not provide information regarding the operational status of the laboratory or any specific business opening dates.
What is UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room?
UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room is a renovation/alteration project at 221 9th Street in Galveston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Renovation of Galveston National Laboratory Level 2, including the addition of a fumigation room and trench drain in the BSL-4 laboratory
Is UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room open in Galveston?
Construction on UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.
Where is UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room located?
UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room is located at 221 9th Street, Galveston, TX, 77555, in Galveston County.
Who is the owner or developer of UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room?
UTMB is the property owner/developer of record for UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room, per its TDLR project registration.
Who is the architect or design firm for UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room?
Perkins&Will is the design firm of record for UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room, according to its TDLR filing.
How much does UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room cost and how big is it?
UTMB G20 Grant Submission:Conversion of Animal Room 2.300 to Fumigation Room has an estimated construction value of $1.5M and approximately 360 square feet (about $4.17K/sqft), based on its TDLR filing.
Scope of Work
Renovation of Galveston National Laboratory Level 2, including the addition of a fumigation room and trench drain in the BSL-4 laboratory
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
221 9th Street, Galveston, TX, 77555
Related Projects
Same Owner
$169.4M totalWatch all construction in 77555 (Galveston)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Galveston?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.