Mike Shaw Toyota QL Expansion
Mike Shaw Toyota QL Expansion is a renovation/alteration project at 3232 I-69 Access Rd. 3232 I-69 Access Rd., Robstown, in Nueces County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jan 2026). The project has an estimated value of $1.1M across about 1,002 sq ft.
๐Project Metrics
TDLR #TABS2023027256Project Closed
Project has been completed and closed
Mike Shaw Toyota QL Expansion is a Renovation/Alteration project located at 3232 I-69 Access Rd. 3232 I-69 Access Rd., Robstown, TX 78380 in Robstown, Texas. The project has an estimated value of $1.1M covering 1,002 sq ft. Mike Shaw is the property owner and Goree Architects, Inc. is the design firm of record. The project was registered with TDLR on August 31, 2023.
โFrequently Asked Questions
What is Mike Shaw Toyota QL Expansion?
Mike Shaw Toyota QL Expansion is a renovation/alteration project at 3232 I-69 Access Rd. 3232 I-69 Access Rd. in Robstown, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Approved changes removed renovations to the interior of the service lounge from the Scope of Work. The planned Quicklane Expansion was not altered from the submitted Scope of Work.
Is Mike Shaw Toyota QL Expansion open in Robstown?
Construction on Mike Shaw Toyota QL Expansion is complete โ TDLR records show the project passed its required accessibility inspection in Jan 2026. The building is finished and very likely open.
Where is Mike Shaw Toyota QL Expansion located?
Mike Shaw Toyota QL Expansion is located at 3232 I-69 Access Rd. 3232 I-69 Access Rd., Robstown, TX, 78380, in Nueces County.
Who is the owner or developer of Mike Shaw Toyota QL Expansion?
Mike Shaw is the property owner/developer of record for Mike Shaw Toyota QL Expansion, per its TDLR project registration.
Who is the architect or design firm for Mike Shaw Toyota QL Expansion?
Goree Architects, Inc. is the design firm of record for Mike Shaw Toyota QL Expansion, according to its TDLR filing.
How much does Mike Shaw Toyota QL Expansion cost and how big is it?
Mike Shaw Toyota QL Expansion has an estimated construction value of $1.1M and approximately 1,002 square feet (about $1.10K/sqft), based on its TDLR filing.
๐Scope of Work
Approved changes removed renovations to the interior of the service lounge from the Scope of Work. The planned Quicklane Expansion was not altered from the submitted Scope of Work.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐ Project Timeline
Filed
Aug 31, 2023
Review Complete
Inspection Complete
Oct 6, 2024
Closed
Jan 22, 2026