Port Arthur Fire Station No. 3 and Storage Building

2385 61st Street, Port Arthur, TX, 77640

Construction complete · Jun 2026Inspection Complete

Port Arthur Fire Station No. 3 and Storage Building is a new construction project at 2385 61st Street, Port Arthur, in Jefferson County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jun 2026). The project has an estimated value of $10.2M across about 15,349 sq ft.

Estimated project value
$10.2M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
15,349 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$666/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1 year
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jan 24, 2024885 days across supplied datesJun 27, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    68 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    365 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    452 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Port Arthur Fire Station No. 3 and Storage Building

The new Fire Station No. 3 in Port Arthur has passed its final TDLR accessibility inspection, confirming that construction is complete. Located at 2385 61st Street, this 15,349 sq ft facility was built by the City of Port Arthur to serve Jefferson County with modern emergency response capabilities. The project, filed as Port Arthur Fire Station No. 3 and Storage Building, represents a significant investment in local public safety infrastructure.

Scope and Design

Brown Reynolds Watford Archtiects served as the design firm of record for this new construction project. The scope includes sleeping quarters for eight personnel and a dedicated community room, ensuring the station supports both operational needs and public engagement. Eddie Hare was the registered accessibility specialist for the project. The total estimated cost was $10,225,000, which calculates to $666 per square foot.

Construction began in April 2024, following a TDLR registration in January 2024. The scheduled build window of 365 days is longer than the 242-day median for new construction projects in Jefferson County. The project cost is above the county median of $750,000, placing it in the top quarter of similar filings. The $666 per square foot cost is also above the county median of $145 per square foot.

Regional Context

The City of Port Arthur has six other TDLR-registered projects totaling $19,383,486, including the nearby Fire Station No. 2 valued at $11,250,000. Brown Reynolds Watford Archtiects has completed three other projects in the region, including the Deer Park Fire Station 1. The project utilized public funds and public land. Jefferson County had an unemployment rate of 5 percent in July 2026. The ZIP code 77640 has a population of about 17,480 and a median household income of $50,832 according to U.S. Census estimates.

The final TDLR accessibility inspection was passed in June 2026. The TDLR status is Inspection Complete. This confirms the building meets state accessibility standards. The project is a one-off new construction rather than a renovation, reflecting a fresh build for the city's fire department.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77640 (Port Arthur)

One email per change. Unsubscribe in one click. Privacy.

Port Arthur Fire Station No. 3 and Storage Building is a New Construction project located at 2385 61st Street, Port Arthur, TX 77640 in Port Arthur, Texas. The project has an estimated value of $10.2M covering 15,349 sq ft. City of Port Arthur is the property owner and Brown Reynolds Watford Archtiects is the design firm of record. The project was registered with TDLR on January 24, 2024.

Frequently Asked Questions

Is Fire Station No. 3 in Port Arthur open?

The construction is complete and the final TDLR accessibility inspection was passed in June 2026. The TDLR record confirms the building is finished, but does not specify operational hours or public opening dates.

How much did the Port Arthur Fire Station No. 3 cost?

The estimated cost for the new construction was $10,225,000. This amounts to $666 per square foot for the 15,349 sq ft facility, which is above the Jefferson County median for similar projects.

Who designed the new Fire Station No. 3?

Brown Reynolds Watford Archtiects was the design firm of record. Eddie Hare served as the registered accessibility specialist. The City of Port Arthur is the owner of the project.

When was the final inspection for this project?

The final TDLR accessibility inspection was passed in June 2026. The TDLR status is listed as Inspection Complete, indicating the project has finished all required state reviews.

What is the address of Port Arthur Fire Station No. 3?

The address is 2385 61st Street, Port Arthur, TX 77640. It is located in Jefferson County and serves the local community with new emergency response facilities.

What is Port Arthur Fire Station No. 3 and Storage Building?

Port Arthur Fire Station No. 3 and Storage Building is a new construction project at 2385 61st Street in Port Arthur, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New Construction of Port Arthur Fire Station 3 with sleeping for 8 personnel and community room.

Is Port Arthur Fire Station No. 3 and Storage Building open in Port Arthur?

Construction on Port Arthur Fire Station No. 3 and Storage Building is complete — TDLR records show the project passed its required accessibility inspection in Jun 2026. The building is finished and very likely open.

Where is Port Arthur Fire Station No. 3 and Storage Building located?

Port Arthur Fire Station No. 3 and Storage Building is located at 2385 61st Street, Port Arthur, TX, 77640, in Jefferson County.

Who is the owner or developer of Port Arthur Fire Station No. 3 and Storage Building?

City of Port Arthur is the property owner/developer of record for Port Arthur Fire Station No. 3 and Storage Building, per its TDLR project registration.

Who is the architect or design firm for Port Arthur Fire Station No. 3 and Storage Building?

Brown Reynolds Watford Archtiects is the design firm of record for Port Arthur Fire Station No. 3 and Storage Building, according to its TDLR filing.

How much does Port Arthur Fire Station No. 3 and Storage Building cost and how big is it?

Port Arthur Fire Station No. 3 and Storage Building has an estimated construction value of $10.2M and approximately 15,349 square feet (about $666/sqft), based on its TDLR filing.

Scope of Work

New Construction of Port Arthur Fire Station 3 with sleeping for 8 personnel and community room.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

2385 61st Street, Port Arthur, TX, 77640

Location by street address

Watch all construction in 77640 (Port Arthur)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Port Arthur?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.