๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

CoolSys Energy Design Interior Finish Out

7330 San Pedro Ave., Suite 350, San Antonio, TX 78216, San Antonio, TX, 78216
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024012345
$165K
Project Value
5,227
Square Feet
$32/sqft
Cost/SqFt
4 months
Duration
Registered:Feb 26, 2024
Start:Apr 1, 2024
Target:Jul 31, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

5,227 SF INTERIOR FINISH OUT OF PROFESSIONAL ENGINEERING FIRM OFFICE.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 26, 2024
Construction Start
April 1, 2024
Expected Completion
July 31, 2024