From: SH 288 To: Spur 5, Houston, TX 77023, Houston, TX, 77023
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024016939
$46.7M
Project Value
104,992
Square Feet
$445/sqft
Cost/SqFt
2y 5mo
Duration
Registered:Apr 24, 2024
Start:Oct 1, 2024
Target:Mar 1, 2027
Remaining:429 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Full pavement and sidewalk reconstruction, upgrade drainage, signals, signs, pavement markings and construction of pump station.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 24, 2024
Construction Start
October 1, 2024
Expected Completion
March 1, 2027