Chisholm Hall Phase 3 ADA Restrooms
One UTSA Circle, San Antonio, TX 78249, San Antonio, TX, 78249
Completed100%
๐Project Metrics
TDLR #TABS2024018343$400K
Project Value
1,850
Square Feet
$216/sqft
Cost/SqFt
8 months
Duration
Registered:May 13, 2024
Start:May 15, 2024
Target:Dec 31, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Renovation to 5 existing dorm room/restrooms to make ADA compliant. Improvement will include new lighting, mechanical to support 3 roll in showers and 2 3x3 showers with bench. 8 new communication device locations in building.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 13, 2024
Construction Start
May 15, 2024
Expected Completion
December 31, 2024
๐Related Projects
๐คSame Owner
$29.3M totalProperty Owner
๐ค
UTSA
Contact: Eva Arroyo
4 projects ยท $29.3M
View all projects
One UTSA Circle, San Antonio, Texas 78249
Design Firm
๐๏ธ
CHESNEY MORALES PARTNER
4 projects ยท $8.9M
View company profile
4901 Broadway, Suite 250, San Antonio, Texas 78209