๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Outlook Building 6 2nd Floor Finish Out

13701 Woodway Dr., Woodway, TX 76712, Woodway, TX, 76712
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024021168
$300K
Project Value
8,669
Square Feet
$35/sqft
Cost/SqFt
6 months
Duration
Registered:Jun 19, 2024
Start:Aug 1, 2024
Target:Feb 1, 2025
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Finish out of existing, never finished, vacant lease spaces into offices

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 19, 2024
Construction Start
August 1, 2024
Expected Completion
February 1, 2025