Project intelligenceTDLR TABS2024022180Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Fort Bend ISD | Quail Valley Middle School Renovations in Missouri City, TX

3019 FM 1092, Missouri City, TX, 77459

Construction complete · Jun 2026Project Closed

Fort Bend ISD | Quail Valley Middle School Renovations is a renovation/alteration project at 3019 FM 1092, Missouri City, in Fort Bend County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jun 2026). The project has an estimated value of $374K across about 1,656 sq ft.

Estimated project value
$374K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
1,656 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$226/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 8mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jul 1, 2024719 days across supplied datesJun 20, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    119 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    600 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

📰About Fort Bend ISD | Quail Valley Middle School Renovations

Fort Bend ISD | Quail Valley Middle School Renovations is a completed accessibility project located at 3019 FM 1092 in Missouri City, Texas. The registered accessibility specialist, Laura Fulkerson, oversaw the work for the owner, Fort Bend ISD, with design by Huckabee. The project involved renovation and alteration of a 1,656-square-foot educational facility. The estimated cost was $373,653, resulting in a cost per square foot of $226. The project was registered with TDLR in July 2024. Construction started in October 2024 and the TDLR status is Project Closed.

Project Scope and Financials

The filing describes the scope as Fort Bend ISD | Quail Valley Middle School Renovations. The total estimated cost of $373,653 is above the county median for its type. The scheduled build window of 600 days is longer than the county median of 92 days. The $226 per square foot is above the county median of $80. The project involves public funds, public land, or is a Federally funded roadway project. It is located outside the FEMA Special Flood Hazard Area (zone X).

Owner and Design Firm History

Fort Bend ISD has six other TDLR-registered projects totaling $2,482,065. These include Walker Station Elementary School in Sugar Land for $416,958 with review complete. Brazos Bend Elementary School in Sugar Land is $179,700 with review complete. Colony Meadow Elementary School in Sugar Land is $506,963 with review complete. Oyster Creek Elementary School in Sugar Land is $157,916 with review complete. Colony Bend Elementary School in Sugar Land is $917,140.

Huckabee has six other TDLR-registered projects totaling $139,300,000. Trinity High School in Euless is $4,000,000 with project registered. Jarrell ISD | Atlas Ranch Elementary School in Jarrell is $48,000,000 with review complete. Gatesville ISD | Junior High Expansion and Renovation in Gatesville is $14,600,000 with review complete. Gatesville ISD | High School - New Field House in Gatesville is $6,900,000 with project registered. Venus High School in Venus is $63,800,000 with review complete.

The project was registered with TDLR in July 2024. The completion date on the filing was June 2026. The TDLR file closed in June 2026. The TDLR closed the project file in June 2026, which marks the end of the accessibility review process for this construction. A post by the Fort Bend ISD noted that Quail Valley Middle School students are benefitting from new and renovated fine arts spaces made possible through funding from the 2023 Bond.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77459 (Missouri City)

One email per change. Unsubscribe in one click. Privacy.

Fort Bend ISD | Quail Valley Middle School Renovations is a Renovation/Alteration project located at 3019 FM 1092, Missouri City, TX 77459 in Missouri City, Texas. The project has an estimated value of $374K covering 1,656 sq ft. Fort Bend ISD is the property owner and Huckabee is the design firm of record. The project was registered with TDLR on July 1, 2024.

Frequently Asked Questions

Who is the registered accessibility specialist for this project?

Laura Fulkerson is the registered accessibility specialist for the Fort Bend ISD | Quail Valley Middle School Renovations project in Missouri City.

What is the total estimated cost of the renovation?

The estimated cost for the Quail Valley Middle School renovations is $373,653. The project covers 1,656 square feet at a cost of $226 per square foot.

When did construction start and finish?

Construction started in October 2024. The completion date on the filing was June 2026. The TDLR closed the project file in June 2026.

Is the project located in a flood zone?

The project is located outside the FEMA Special Flood Hazard Area (zone X). It is not in the FEMA 1-percent-annual-chance floodplain.

Who designed the Quail Valley Middle School renovations?

Huckabee is the design firm of record for the Fort Bend ISD | Quail Valley Middle School Renovations project in Missouri City, Texas.

What is Fort Bend ISD | Quail Valley Middle School Renovations?

Fort Bend ISD | Quail Valley Middle School Renovations is a renovation/alteration project at 3019 FM 1092 in Missouri City, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Fort Bend ISD | Quail Valley Middle School Renovations

Is Fort Bend ISD | Quail Valley Middle School Renovations open in Missouri City?

Construction on Fort Bend ISD | Quail Valley Middle School Renovations is complete — TDLR records show the project passed its required accessibility inspection in Jun 2026. The building is finished and very likely open.

Where is Fort Bend ISD | Quail Valley Middle School Renovations located?

Fort Bend ISD | Quail Valley Middle School Renovations is located at 3019 FM 1092, Missouri City, TX, 77459, in Fort Bend County.

Who is the owner or developer of Fort Bend ISD | Quail Valley Middle School Renovations?

Fort Bend ISD is the property owner/developer of record for Fort Bend ISD | Quail Valley Middle School Renovations, per its TDLR project registration.

Who is the architect or design firm for Fort Bend ISD | Quail Valley Middle School Renovations?

Huckabee is the design firm of record for Fort Bend ISD | Quail Valley Middle School Renovations, according to its TDLR filing.

How much does Fort Bend ISD | Quail Valley Middle School Renovations cost and how big is it?

Fort Bend ISD | Quail Valley Middle School Renovations has an estimated construction value of $374K and approximately 1,656 square feet (about $226/sqft), based on its TDLR filing.

Scope of Work

Fort Bend ISD | Quail Valley Middle School Renovations

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

3019 FM 1092, Missouri City, TX, 77459

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 77459 (Missouri City)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Missouri City?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.