Fleming Elementary School Interior Renovation in Houston, TX
14850 Bissonnet, Houston, TX, 77083
Fleming Elementary School Interior Renovation is a renovation/alteration project at 14850 Bissonnet, Houston, in Fort Bend County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $1.1M across about 55,366 sq ft.
- Estimated project value
- $1.1M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 55,366 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $20/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 1y 2mo
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
6 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
Same day as the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
123 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
421 days after the preceding date shown.
Source: TDLR filing
View source recordInspection complete · TDLR filing
The filing records completion of the accessibility inspection.
97 days after the preceding date shown.
Source: TDLR filing
View source recordProject closed · TDLR filing
The project record was closed in TDLR.
147 days after the preceding date shown.
Source: TDLR filing
View source record
📰About Fleming Elementary School Interior Renovation
Fleming Elementary School in Houston, Texas, completed a $1,088,737 interior renovation at 14850 Bissonnet. The project, filed as Fleming Elementary School Interior Renovation, covered 55,366 square feet of instructional space within Fort Bend County. TDLR closed the project file in September 2026, which marks the end of the accessibility review process for this construction.
The scope of work focused on updating the learning environment for students and staff. Contractors removed and replaced flooring and base throughout all classrooms and corridors. The project also included the replacement of interior doors and door hardware to meet current accessibility standards. During the demolition and installation phases, furniture was relocated across the campus to maintain safety and workflow.
Fort Bend ISD served as the owner of record for this public facility. PBK Architects acted as the design firm, overseeing the planning and execution of the renovation. William T Winning was the registered accessibility specialist associated with the filing. The project utilized public funds, reflecting the district’s commitment to maintaining modern, accessible educational infrastructure in the Houston area.
The timeline for this renovation spanned from a scheduled construction start in December 2024 to a final inspection passed in May 2026. The filing indicated a completion date of January 2026, but the official final inspection occurred in May 2026. This extended schedule allowed for thorough execution of the flooring and hardware updates across the large square footage. The cost of $20 per square foot is below the county median of $80 per square foot for similar renovation and alteration projects in Fort Bend County.
Fleming Elementary is one of several recent projects by Fort Bend ISD in the region. The district has registered other renovations at nearby schools such as Walker Station Elementary and Brazos Bend Elementary in Sugar Land. PBK Architects has also designed significant projects for other Texas districts, including Royal STEM Academy in Brookshire and Paul Scherer Memorial Stadium in Richmond. The completion of this project ensures that Fleming Elementary meets the latest accessibility requirements for its students and community.
Project Closed
Project has been completed and closed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 77083 (Houston)
One email per change. Unsubscribe in one click. Privacy.
Fleming Elementary School Interior Renovation is a Renovation/Alteration project located at 14850 Bissonnet, Houston, TX 77083 in Houston, Texas. The project has an estimated value of $1.1M covering 55,366 sq ft. Fort Bend ISD is the property owner and PBK Architects is the design firm of record. The project was registered with TDLR on August 2, 2024.
Frequently Asked Questions
Is Fleming Elementary School open?
The TDLR record confirms the construction project is complete and the file is closed. It does not provide information about daily school operations or specific opening hours for the public.
What work was done at Fleming Elementary?
The renovation involved removing and replacing flooring and base in classrooms and corridors. It also included replacing interior doors and hardware, with furniture relocated during the process.
Who designed the renovation project?
PBK Architects was the design firm of record for the project. William T Winning served as the registered accessibility specialist for the TDLR filing.
When was the final inspection passed?
The final inspection for the Fleming Elementary School Interior Renovation was passed in May 2026. TDLR closed the project file in September 2026.
How much did the renovation cost?
The estimated cost for the project was $1,088,737. This translates to approximately $20 per square foot for the 55,366 square feet of work.
What is Fleming Elementary School Interior Renovation?
Fleming Elementary School Interior Renovation is a renovation/alteration project at 14850 Bissonnet in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Remove and replace flooring and base throughout classrooms and corridors. replace interior doors and door hardware. relocate furniture within campus while flooring is being demolished and replaced.
Is Fleming Elementary School Interior Renovation open in Houston?
Construction on Fleming Elementary School Interior Renovation is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.
Where is Fleming Elementary School Interior Renovation located?
Fleming Elementary School Interior Renovation is located at 14850 Bissonnet, Houston, TX, 77083, in Fort Bend County.
Who is the owner or developer of Fleming Elementary School Interior Renovation?
Fort Bend ISD is the property owner/developer of record for Fleming Elementary School Interior Renovation, per its TDLR project registration.
Who is the architect or design firm for Fleming Elementary School Interior Renovation?
PBK Architects is the design firm of record for Fleming Elementary School Interior Renovation, according to its TDLR filing.
How much does Fleming Elementary School Interior Renovation cost and how big is it?
Fleming Elementary School Interior Renovation has an estimated construction value of $1.1M and approximately 55,366 square feet (about $20/sqft), based on its TDLR filing.
Scope of Work
Remove and replace flooring and base throughout classrooms and corridors. replace interior doors and door hardware. relocate furniture within campus while flooring is being demolished and replaced.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
14850 Bissonnet, Houston, TX, 77083
Explore the supplied address
A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.
Related Projects
Same Owner
$47.53B totalWatch all construction in 77083 (Houston)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Houston?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.