Project intelligenceTDLR TABS2024025885Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Judson Independent School District Gymnasium HVAC Upgrades Phase 2

3635 Candleglenn, San Antonio, TX, 78244

Construction complete · Sep 2026Project Closed

Judson Independent School District Gymnasium HVAC Upgrades Phase 2 is a renovation/alteration project at 3635 Candleglenn, San Antonio, in Bexar County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $394K across about 5,000 sq ft.

Estimated project value
$394K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
5,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$79/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1 year
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Aug 20, 2024751 days across supplied datesSep 10, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    103 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    365 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  5. Project closed · TDLR filing

    The project record was closed in TDLR.

    283 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Judson Independent School District Gymnasium HVAC Upgrades Phase 2

Judson Independent School District completed a $393,984 renovation at Candlewood Elementary School in San Antonio, focusing on cooling upgrades for the gymnasium. The project, filed with the Texas Department of Licensing and Regulation (TDLR) in August 2024, involved a 5,000 sq ft alteration to improve climate control in a high-occupancy space. The work concluded in December 2025, with the TDLR status marked as Project Closed.

The scope of work required the demolition of existing unit heaters and ventilation fans within the gym. Crews then installed a roof-mounted rooftop unit (RTU) outside the structure and routed new ductwork inside to provide consistent cooling. The installation also involved extending gas lines along the roof to service the new mechanical equipment. This shift from localized unit heaters to a centralized HVAC system represents a significant infrastructure update for the school's athletic and assembly spaces.

Project Details and Cost Context

The estimated cost of $393,984 places this renovation above the median estimated cost of $250,000 for similar renovation and alteration filings in Bexar County. The project size of 5,000 sq ft is larger than the county median of 4,115 sq ft. However, the cost per square foot of $79 is close to the county median of $85. The scheduled build window of 365 days was longer than the county median of 103 days, reflecting the complexity of integrating roof-mounted equipment and interior ductwork in an occupied school environment.

Cleary Zimmermann Engineers served as the design firm of record for this project. The firm has been involved in six other TDLR-registered projects totaling $6,621,671, including work at Hobby Middle School and the International Advanced Technology Center. Judson ISD, the owner of record, has six other TDLR-registered projects totaling $38,845,158, indicating a sustained capital improvement program across its campuses. The project involved public funds, consistent with the district's status as a public school entity.

According to TDLR records, the final inspection was passed in December 2025. TDLR closed the project file in September 2026, which marks the end of the accessibility review process for this construction. The project is located at 3635 Candleglenn in San Antonio, within Bexar County. City of San Antonio permit records show one permit on file at this street address, issued between April 2026 and April 2026, for an On Premise Sign.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78244 (San Antonio)

One email per change. Unsubscribe in one click. Privacy.

Judson Independent School District Gymnasium HVAC Upgrades Phase 2 is a Renovation/Alteration project located at 3635 Candleglenn, San Antonio, TX 78244 in San Antonio, Texas. The project has an estimated value of $394K covering 5,000 sq ft. JUDSON ISD is the property owner and Cleary Zimmermann Engineers is the design firm of record. The project was registered with TDLR on August 20, 2024.

Frequently Asked Questions

What work was done to the gymnasium?

Existing unit heaters and ventilation fans were demolished. A roof-mounted RTU was installed outside, and ductwork was routed inside the gym to provide cooling. Gas lines were extended along the roof to service the new equipment.

Who designed the project?

Cleary Zimmermann Engineers is the design firm of record. The owner of record is Judson Independent School District. The project was registered with TDLR in August 2024.

Is the project finished?

Yes. The final inspection was passed in December 2025. TDLR closed the project file in September 2026, marking the end of the accessibility review process for this construction.

How much did the renovation cost?

The estimated cost was $393,984. This is above the county median for similar filings, but the cost per square foot of $79 is close to the county median of $85.

What is the address?

The project is located at 3635 Candleglenn, San Antonio, TX 78244. It is a renovation/alteration project at Candlewood Elementary School.

What is Judson Independent School District Gymnasium HVAC Upgrades Phase 2?

Judson Independent School District Gymnasium HVAC Upgrades Phase 2 is a renovation/alteration project at 3635 Candleglenn in San Antonio, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Demolish existing unit heaters and ventilation fans in gym. Install roof mounted RTU outside gym and route ductwork inside gym to provide cooling. Extend gas along roof to RTU. 5000 sqft.

Is Judson Independent School District Gymnasium HVAC Upgrades Phase 2 open in San Antonio?

Construction on Judson Independent School District Gymnasium HVAC Upgrades Phase 2 is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.

Where is Judson Independent School District Gymnasium HVAC Upgrades Phase 2 located?

Judson Independent School District Gymnasium HVAC Upgrades Phase 2 is located at 3635 Candleglenn, San Antonio, TX, 78244, in Bexar County.

Who is the owner or developer of Judson Independent School District Gymnasium HVAC Upgrades Phase 2?

JUDSON ISD is the property owner/developer of record for Judson Independent School District Gymnasium HVAC Upgrades Phase 2, per its TDLR project registration.

Who is the architect or design firm for Judson Independent School District Gymnasium HVAC Upgrades Phase 2?

Cleary Zimmermann Engineers is the design firm of record for Judson Independent School District Gymnasium HVAC Upgrades Phase 2, according to its TDLR filing.

How much does Judson Independent School District Gymnasium HVAC Upgrades Phase 2 cost and how big is it?

Judson Independent School District Gymnasium HVAC Upgrades Phase 2 has an estimated construction value of $394K and approximately 5,000 square feet (about $79/sqft), based on its TDLR filing.

Scope of Work

Demolish existing unit heaters and ventilation fans in gym. Install roof mounted RTU outside gym and route ductwork inside gym to provide cooling. Extend gas along roof to RTU. 5000 sqft.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

3635 Candleglenn, San Antonio, TX, 78244

Location by street address

Watch all construction in 78244 (San Antonio)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in San Antonio?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.