๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
A New Gymnasium for Nocona ISD
1012 Clay, Nocona, TX 76225, Nocona, TX, 76225
Construction50%
๐Project Metrics
TDLR #TABS2024026753$6.5M
Project Value
21,885
Square Feet
$297/sqft
Cost/SqFt
2 years
Duration
Registered:Aug 30, 2024
Start:Oct 1, 2024
Target:Oct 1, 2026
Remaining:279 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New Gymnasium (21,885 sq.ft.)
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 30, 2024
Construction Start
October 1, 2024
Expected Completion
October 1, 2026
๐Related Projects
๐คSame Owner
$18.0M totalProperty Owner
๐ค
NOCONA ISD
Contact: David Waters
3 projects ยท $18.0M
View company profile
1012 Clay, Nocona, Texas 76225
Design Firm
๐๏ธ
Harper Perkins Architects
4 projects ยท $25.3M
View company profile
4724 Old Jacksboro Hwy., Wichita Falls, Texas 76302