Project intelligenceTDLR TABS2025002671Renovation/Alteration
Funding type

This project is privately funded, on private land for private use.

PS3-1 CSC Lab Expansion in Austin, TX

701 E Parmer Ln Bld 3, Austin, TX, 78758

Target date passed (May 2025)Review Complete

PS3-1 CSC Lab Expansion is a renovation/alteration project at 701 E Parmer Ln Bld 3, Austin, in Travis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish May 2025 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $754K across about 3,205 sq ft.

Estimated project value
$754K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
3,205 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$235/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
5 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 8, 2024213 days across supplied datesMay 9, 2025

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    55 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    158 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About PS3-1 CSC Lab Expansion

Dell Technologies is executing a $753,700 renovation of Building 3 at 701 E Parmer Ln in Austin. The project, filed as PS3-1 CSC Lab Expansion, covers 3,205 sq ft of interior space within the Parmer North area. This work is classified as a renovation and alteration, focusing on the modernization of existing laboratory and office infrastructure for private use.

The scope includes limited demolition and the construction of new partitions, ceilings, and finishes. Interior updates involve new MEP equipment, while exterior work comprises new concrete pads, mechanical equipment installation, and landscape screening. The estimated cost of $235 per square foot is above the Travis County median of $104 for similar renovation filings. The scheduled build window of 158 days is also longer than the county median of 98 days.

Project Status and Timeline

TDLR completed plan review in October 2024, and construction was scheduled to finish in May 2025. However, TDLR has not yet recorded a final inspection, so the current state of the site is not confirmed in the public record. The project was registered with TDLR in October 2024, with a construction start date of December 2024 per the filing.

Cushing Terrell serves as the design firm of record for this project. Mark S Robinson is the registered accessibility specialist. Dell Technologies has six other TDLR-registered projects, including large-scale developments in Round Rock and Austin, totaling $18,345,000. Cushing Terrell has six other registered projects, including the Sail Tower in Austin, totaling $32,916,082.

City of Austin permit records show at least 25 permits on file at this street address. The 25 most recent were issued between March 2025 and August 2026, including mechanical, building, electrical, and plumbing permits. Four of these permits have a final status.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78758 (Austin)

One email per change. Unsubscribe in one click. Privacy.

PS3-1 CSC Lab Expansion is a Renovation/Alteration project located at 701 E Parmer Ln Bld 3, Austin, TX 78758 in Austin, Texas. The project has an estimated value of $754K covering 3,205 sq ft. Dell Technologies is the property owner and Cushing Terrell is the design firm of record. The project was registered with TDLR on October 8, 2024.

Frequently Asked Questions

What is the current status of the PS3 project at 701 E Parmer Ln?

TDLR completed plan review in October 2024, and construction was scheduled to finish in May 2025. However, TDLR has not yet recorded a final inspection, so the current state of the site is not confirmed in the public record.

Who is the owner and design firm for this renovation?

Dell Technologies is the owner of record. Cushing Terrell is the design firm of record for the project.

How much does the project cost and what is the size?

The estimated cost is $753,700 for 3,205 sq ft. This equates to $235 per square foot, which is above the Travis County median for similar renovation filings.

Is the business open at this location?

The TDLR record indicates construction was scheduled to finish in May 2025, but no final inspection has been recorded. Therefore, the operational status of the business is not confirmed in the public construction record.

What type of work is being performed?

The work includes limited demolition, new partitions, ceilings, finishes, and new MEP equipment. Exterior work includes concrete pads, mechanical equipment, and landscape screening.

What is PS3-1 CSC Lab Expansion?

PS3-1 CSC Lab Expansion is a renovation/alteration project at 701 E Parmer Ln Bld 3 in Austin, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Limited demolition, construction of new partitions, ceilings, finishes, new MEP equipment. Exterior work included construction of new concrete pads, installation of mechanical equipment and installation of new landscape and screening ele…

Is PS3-1 CSC Lab Expansion open in Austin?

PS3-1 CSC Lab Expansion was scheduled to finish construction in May 2025 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is PS3-1 CSC Lab Expansion located?

PS3-1 CSC Lab Expansion is located at 701 E Parmer Ln Bld 3, Austin, TX, 78758, in Travis County.

Who is the owner or developer of PS3-1 CSC Lab Expansion?

Dell Technologies is the property owner/developer of record for PS3-1 CSC Lab Expansion, per its TDLR project registration.

Who is the architect or design firm for PS3-1 CSC Lab Expansion?

Cushing Terrell is the design firm of record for PS3-1 CSC Lab Expansion, according to its TDLR filing.

How much does PS3-1 CSC Lab Expansion cost and how big is it?

PS3-1 CSC Lab Expansion has an estimated construction value of $754K and approximately 3,205 square feet (about $235/sqft), based on its TDLR filing.

Scope of Work

Limited demolition, construction of new partitions, ceilings, finishes, new MEP equipment. Exterior work included construction of new concrete pads, installation of mechanical equipment and installation of new landscape and screening elements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

701 E Parmer Ln Bld 3, Austin, TX, 78758

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Related City Permits

Building permits found at or near this location

7013 BEACH GRASS DR

*Green Building* New 1-story 4 bedroom 3 bathroom single family residence with attached garage covered front porch and rear covered patio.

ActiveElectrical PermitNewNov 2026
View Details
2026-131419 EP
IES Residential, Inc.
7013 BEACH GRASS DR

*Green Building* New 1-story 4 bedroom 3 bathroom single family residence with attached garage covered front porch and rear covered patio.

ActiveBuilding PermitNewNov 2026
View Details
2026-131419 BP
DRB Homes**MAIN**
7013 BEACH GRASS DR

*Green Building* New 1-story 4 bedroom 3 bathroom single family residence with attached garage covered front porch and rear covered patio.

ActiveMechanical PermitNewNov 2026
View Details
2026-131419 MP
Airtron
7013 BEACH GRASS DR

*Green Building* New 1-story 4 bedroom 3 bathroom single family residence with attached garage covered front porch and rear covered patio.

ActivePlumbing PermitNewNov 2026
View Details
2026-132165 PP
Mustang Plumbing
7010 W SH 71 UNIT 160

CHANGE OF USE MEDICAL OFFICE TO NAIL SALON

ActivePlumbing PermitRemodelOct 2026
View Details
2026-139235 PP
J.R. Maldonado, Plumber

Watch all construction in 78758 (Austin)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.