Take 5 Oil Change - San Antonio, TX (Walzem)

5331 WALZEM RD, San Antonio, TX, 78212

Target date passed (May 2026)Review Complete

Take 5 Oil Change - San Antonio, TX (Walzem) is a new construction project at 5331 WALZEM RD, San Antonio, in Bexar County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish May 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $500K across about 1,682 sq ft.

Estimated project value
$500K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
1,682 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$297/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 6mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Nov 26, 2024541 days across supplied datesMay 21, 2026

4 timeline dates shown.

  1. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR filing

    View source record
  2. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    6 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    535 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Take 5 Oil Change - San Antonio, TX (Walzem)

Take 5 Oil Change is building a new express oil change facility at 5331 Walzem Rd in San Antonio. The project, filed under the name "Take 5 Oil Change - San Antonio, TX (Walzem)," involves the construction of a 1,682 sq ft building with three service bays. The estimated cost for this new construction is $500,000, which works out to $297 per square foot.

Project Scope and Costs

The owner of record is Take 5 Properties SPV, while Altar Group serves as the design firm. Kari Thomas is the registered accessibility specialist for the project. The filing notes that the project involves public funds, public land, or is a Federally funded roadway project. Compared to 8,300 other TDLR-registered new construction filings in Bexar County, this project’s estimated cost is below the county median of $600,000. However, the cost per square foot of $297 is above the county median of $115. The scheduled build window of 541 days is longer than the county median of 208 days.

Take 5 Properties SPV has six other TDLR-registered projects totaling $4,500,000, including locations in Fort Worth, Levelland, and Arlington. Altar Group has six other registered projects totaling $3,085,000, with sites in Houston, Cleveland, Ennis, Willis, and Harker Heights. Other registered projects in the same area include renovations for Prologis Eisenhauer 35, Octapharma Plasma, PECO Pallets, JC Food Mart, and Teamsters Local 657. Nearby businesses include TruFit Athletic Clubs - Walzem, Harbor Freight, Wingstop, Dunkin', Custom Sounds & Tint - Walzem, and Boardwalk at Windcrest Apartments.

Timeline and Status

The project was registered with TDLR in December 2024. Plan review was completed in December 2024, and construction was scheduled to start in November 2024. The filing lists a completion date of May 2026. TDLR has not yet recorded a final inspection, so the current state of the site is not confirmed in the public record. The TDLR status is Review Complete. The project is part of a broader network of Take 5 Oil Change locations, with a web mention from Cylex US describing the brand as a go-to for fast and simple oil changes in San Antonio.

The area’s ZIP code 78212 has a population of about 26,670, with a median household income of $60,222. There are 13,399 housing units, and the median owner-occupied home value is $299,400. Housing is an even mix of owner- and renter-occupied. The Bexar County unemployment rate was 4.8 percent in June 2026, higher than a year earlier. These Census estimates provide context for the local market where the new facility is being built.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78212 (San Antonio)

One email per change. Unsubscribe in one click. Privacy.

Take 5 Oil Change - San Antonio, TX (Walzem) is a New Construction project located at 5331 WALZEM RD, San Antonio, TX 78212 in San Antonio, Texas. The project has an estimated value of $500K covering 1,682 sq ft. Take 5 Properties SPV is the property owner and Altar Group is the design firm of record. The project was registered with TDLR on December 2, 2024.

Frequently Asked Questions

Is the Take 5 Oil Change at 5331 Walzem Rd open?

TDLR has not yet recorded a final inspection. The filing lists a completion date of May 2026, but the current state of the site is not confirmed in the public record.

How large is the new Take 5 Oil Change building?

The new construction is 1,682 sq ft. It includes three service bays for express oil changes. The estimated cost is $500,000, or $297 per square foot.

Who is the owner and designer of the project?

The owner of record is Take 5 Properties SPV. The design firm of record is Altar Group. Kari Thomas is the registered accessibility specialist.

How does the cost compare to other projects in Bexar County?

The $500,000 estimated cost is below the county median of $600,000. However, the $297 per sq ft cost is above the county median of $115.

What is Take 5 Oil Change - San Antonio, TX (Walzem)?

Take 5 Oil Change - San Antonio, TX (Walzem) is a new construction project at 5331 WALZEM RD in San Antonio, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: NEW EXPRESS OIL CHANGE BUILDING WITH 3 SERVICE BAYS

Is Take 5 Oil Change - San Antonio, TX (Walzem) open in San Antonio?

Take 5 Oil Change - San Antonio, TX (Walzem) was scheduled to finish construction in May 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is Take 5 Oil Change - San Antonio, TX (Walzem) located?

Take 5 Oil Change - San Antonio, TX (Walzem) is located at 5331 WALZEM RD, San Antonio, TX, 78212, in Bexar County.

Who is the owner or developer of Take 5 Oil Change - San Antonio, TX (Walzem)?

Take 5 Properties SPV is the property owner/developer of record for Take 5 Oil Change - San Antonio, TX (Walzem), per its TDLR project registration.

Who is the architect or design firm for Take 5 Oil Change - San Antonio, TX (Walzem)?

Altar Group is the design firm of record for Take 5 Oil Change - San Antonio, TX (Walzem), according to its TDLR filing.

How much does Take 5 Oil Change - San Antonio, TX (Walzem) cost and how big is it?

Take 5 Oil Change - San Antonio, TX (Walzem) has an estimated construction value of $500K and approximately 1,682 square feet (about $297/sqft), based on its TDLR filing.

Scope of Work

NEW EXPRESS OIL CHANGE BUILDING WITH 3 SERVICE BAYS

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

5331 WALZEM RD, San Antonio, TX, 78212

Location by street address

Watch all construction in 78212 (San Antonio)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in San Antonio?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.