Huntwick Ave - S. Staples to Pavement change in Corpus Christi, TX

5500 Huntwick Ave to Pavement change, Corpus Christi, TX, 78413

Construction complete · Mar 2026Inspection Complete

Huntwick Ave - S. Staples to Pavement change is a new construction project at 5500 Huntwick Ave to Pavement change, Corpus Christi, in Nueces County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Mar 2026). The project has an estimated value of $1.3M across about 5,000 sq ft.

Estimated project value
$1.3M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
5,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$265/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
7 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jan 8, 2025419 days across supplied datesMar 3, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    68 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    200 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    151 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Huntwick Ave - S. Staples to Pavement change

The City of Corpus Christi completed the construction of approximately 5,000 square feet of new concrete sidewalk and ADA curb ramps along Huntwick Avenue, extending from S. Staples to the pavement change. This project, valued at $1,325,000, was registered with TDLR in January 2025 and marked a significant infrastructure improvement for the Nueces County area. The work involved new construction rather than renovation, focusing on accessibility compliance and pedestrian safety on a public roadway.

Munoz Engineering served as the design firm of record for this initiative, which was funded through public sources. The registered accessibility specialist for the project was Emily Rozypal. The scheduled build window for the work was 200 days, a duration that is close to the county median of 240 days for similar new construction filings in Nueces County. The estimated cost of $1,325,000 places this project above the county median estimated cost of $662,000 for its type, reflecting the specific scope of civil works involved.

Construction activity began in March 2025, following the completion of plan review in January 2025. The filing indicated a target completion date of October 2025. However, the official record shows that the final TDLR accessibility inspection was passed in March 2026. This confirms that all construction activities were finished and the site met the required accessibility standards prior to this final verification. The TDLR status is now listed as Inspection Complete.

The City of Corpus Christi has several other TDLR-registered projects, including the District 5 Trail and the Don and Sandy Skate Park. Munoz Engineering has also been involved in other local developments, such as the Hawn Boat Facility and the Allison Road Training Facility. This project contributes to the broader network of accessible infrastructure in the Corpus Christi area, specifically within the ZIP code 78413, where the U.S. Census estimates a population of about 35,103 and a median household income of $71,624.

The completion of this sidewalk and curb ramp installation enhances connectivity for residents and visitors in the Huntwick Avenue corridor. The project’s cost per square foot was calculated at $265, which is above the county median of $118 per square foot for similar filings. This variance is typical for projects involving specialized ADA compliance elements and new concrete work in established urban areas. The successful completion of this project adds to the City’s record of maintaining and improving public accessibility standards in Nueces County.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78413 (Corpus Christi)

One email per change. Unsubscribe in one click. Privacy.

Huntwick Ave - S. Staples to Pavement change is a New Construction project located at 5500 Huntwick Ave to Pavement change, Corpus Christi, TX 78413 in Corpus Christi, Texas. The project has an estimated value of $1.3M covering 5,000 sq ft. City of Corpus Christi is the property owner and Munoz Engineering is the design firm of record. The project was registered with TDLR on January 8, 2025.

Frequently Asked Questions

Is the Huntwick Ave sidewalk project finished?

Yes, construction is complete. The project passed its final TDLR accessibility inspection in March 2026, and the TDLR status is listed as Inspection Complete.

Who designed the Huntwick Ave sidewalk project?

Munoz Engineering is the design firm of record for this project. Emily Rozypal served as the registered accessibility specialist.

What is the estimated cost of the project?

The estimated cost for the 5,000 square feet of sidewalk and curb ramps is $1,325,000.

When did construction start and end?

Construction started in March 2025. The final TDLR accessibility inspection was passed in March 2026, confirming completion.

Who owns the Huntwick Ave sidewalk project?

The City of Corpus Christi is the owner/developer of record for this project.

What is Huntwick Ave - S. Staples to Pavement change?

Huntwick Ave - S. Staples to Pavement change is a new construction project at 5500 Huntwick Ave to Pavement change in Corpus Christi, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Approx. 5,000 SF of concrete sidewalk & ADA curb ramps

Is Huntwick Ave - S. Staples to Pavement change open in Corpus Christi?

Construction on Huntwick Ave - S. Staples to Pavement change is complete — TDLR records show the project passed its required accessibility inspection in Mar 2026. The building is finished and very likely open.

Where is Huntwick Ave - S. Staples to Pavement change located?

Huntwick Ave - S. Staples to Pavement change is located at 5500 Huntwick Ave to Pavement change, Corpus Christi, TX, 78413, in Nueces County.

Who is the owner or developer of Huntwick Ave - S. Staples to Pavement change?

City of Corpus Christi is the property owner/developer of record for Huntwick Ave - S. Staples to Pavement change, per its TDLR project registration.

Who is the architect or design firm for Huntwick Ave - S. Staples to Pavement change?

Munoz Engineering is the design firm of record for Huntwick Ave - S. Staples to Pavement change, according to its TDLR filing.

How much does Huntwick Ave - S. Staples to Pavement change cost and how big is it?

Huntwick Ave - S. Staples to Pavement change has an estimated construction value of $1.3M and approximately 5,000 square feet (about $265/sqft), based on its TDLR filing.

Scope of Work

Approx. 5,000 SF of concrete sidewalk & ADA curb ramps

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

5500 Huntwick Ave to Pavement change, Corpus Christi, TX, 78413

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78413 (Corpus Christi)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Corpus Christi?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.