Project intelligenceTDLR TABS2025011018New Construction
Funding type

This project is privately funded, on private land for private use.

Terminal F Baggage Building

2660 South International Parkway, Dfw Airport, TX, 75261

Opening ~May 2028Review Complete

Terminal F Baggage Building is a new construction project at 2660 South International Parkway, Dfw Airport, in Tarrant County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion May 2028. The project has an estimated value of $83.8M across about 173,759 sq ft.

Estimated project value
$83.8M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
173,759 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$482/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
3y 3mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Feb 4, 20251,187 days across supplied datesMay 6, 2028

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    7 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    1,180 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75261 (Dfw Airport)

One email per change. Unsubscribe in one click. Privacy.

Terminal F Baggage Building is a New Construction project located at 2660 South International Parkway, Dfw Airport, TX 75261 in Dfw Airport, Texas. The project has an estimated value of $83.8M covering 173,759 sq ft. DFW Airport is the property owner and Ghafari Associates LLC is the design firm of record. The project was registered with TDLR on February 4, 2025.

Frequently Asked Questions

What is Terminal F Baggage Building?

Terminal F Baggage Building is a new construction project at 2660 South International Parkway in Dfw Airport, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New 3-level baggage handling building for the new DFW Airport Terminal F

Is Terminal F Baggage Building open in Dfw Airport?

Terminal F Baggage Building is still under construction in Dfw Airport, TX, with an estimated completion of May 2028 according to its TDLR registration.

Where is Terminal F Baggage Building located?

Terminal F Baggage Building is located at 2660 South International Parkway, Dfw Airport, TX, 75261, in Tarrant County.

Who is the owner or developer of Terminal F Baggage Building?

DFW Airport is the property owner/developer of record for Terminal F Baggage Building, per its TDLR project registration.

Who is the architect or design firm for Terminal F Baggage Building?

Ghafari Associates LLC is the design firm of record for Terminal F Baggage Building, according to its TDLR filing.

How much does Terminal F Baggage Building cost and how big is it?

Terminal F Baggage Building has an estimated construction value of $83.8M and approximately 173,759 square feet (about $482/sqft), based on its TDLR filing.

Scope of Work

New 3-level baggage handling building for the new DFW Airport Terminal F

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

2660 South International Parkway, Dfw Airport, TX, 75261

Location by street address

Watch all construction in 75261 (Dfw Airport)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Dfw Airport?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.