Project intelligenceTDLR TABS2025016088Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

EPISD Coronado High School, Bldg. A, Custodial and Book Storage in El Paso, TX

100 Champions Place, El Paso, TX, 79912

Construction complete · Apr 2025Project Closed

EPISD Coronado High School, Bldg. A, Custodial and Book Storage is a renovation/alteration project at 100 Champions Place, El Paso, in El Paso County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Apr 2025). The project has an estimated value of $51K across about 190 sq ft.

Estimated project value
$51K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
190 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$268/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
3 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 7, 2025177 days across supplied datesOct 1, 2025

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Project closed · TDLR filing

    The project record was closed in TDLR.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    85 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    92 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About EPISD Coronado High School, Bldg. A, Custodial and Book Storage

The TDLR record for the Coronado High School renovation in El Paso shows that the agency closed the project file in April 2025. This status confirms the end of the accessibility review process for the construction work at 100 Champions Place. The filing identifies the project as EPISD Coronado High School, Bldg. A, Custodial and Book Storage. The work involved a renovation and alteration of the existing facility to accommodate new storage needs.

The scope of work specified the addition of new custodial and book room storage, with each unit measuring 95 square feet. The total square footage for the project was 190 sq ft. The estimated cost for this renovation was $51,000. This figure results in a cost per square foot of $268. The project was registered with TDLR in April 2025, with a construction start date of July 2025 and a scheduled completion date of October 2025.

Project Details and Context

El Paso Independent School District is the owner and developer of record for this project. Carl Daniel Architects served as the design firm of record. Eckhard K Fennig was the registered accessibility specialist for the filing. The project involves public funds and public land. In El Paso County, the median estimated cost for renovation and alteration filings is $203,814. This project's cost is below the county median for its type, placing it in the bottom quarter of comparable filings. The median size for these projects is 3,500 sq ft, while this project is significantly smaller at 190 sq ft.

The median cost per square foot for renovation and alteration projects in El Paso County is $66. The $268 per square foot for the Coronado High School project is above this county median. The scheduled build window for this project was 92 days, which is close to the county median of 120 days for similar work. El Paso Independent School District has six other TDLR-registered projects totaling $16,470,000. These include projects at El Paso High School, Burges High School, Bowie High School, Lamar Elementary School, and Mesita Elementary School.

Carl Daniel Architects has six other TDLR-registered projects totaling $10,430,000. These include work at Del Sol Medical Center and Las Palmas Medical Center. The area profile for ZIP 79912 indicates a population of about 79,126 and a median household income of $72,290. The median owner-occupied home value in this area is $248,400. El Paso County unemployment rate in August 2026 was 4.6 percent, lower than a year earlier. The TDLR file closure in April 2025 marks the final administrative step in the accessibility review for this specific construction scope.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79912 (El Paso)

One email per change. Unsubscribe in one click. Privacy.

EPISD Coronado High School, Bldg. A, Custodial and Book Storage is a Renovation/Alteration project located at 100 Champions Place, El Paso, TX 79912 in El Paso, Texas. The project has an estimated value of $51K covering 190 sq ft. El Paso Independent School District is the property owner and Carl Daniel Architects is the design firm of record. The project was registered with TDLR on April 7, 2025.

Frequently Asked Questions

What was the scope of work for the Coronado High School renovation?

The filing specifies new custodial and book room storage, with each unit measuring 95 square feet. The total project size was 190 sq ft. The work was classified as a renovation and alteration of the existing building.

Who is the owner and design firm for this project?

El Paso Independent School District is the owner and developer of record. Carl Daniel Architects was the design firm of record. Eckhard K Fennig served as the registered accessibility specialist for the TDLR filing.

What was the estimated cost and cost per square foot?

The estimated cost was $51,000. With a total size of 190 sq ft, the cost per square foot was $268. This is above the El Paso County median of $66 for similar renovation projects.

What is the current status of the TDLR filing?

The TDLR closed the project file in April 2025. This marks the end of the accessibility review process. The scheduled completion date was October 2025, and the file status is listed as Project Closed.

Is the Coronado High School renovation complete?

The TDLR record shows the project file was closed in April 2025. The scheduled completion date was October 2025. The status confirms the accessibility review process has ended for this specific scope of work.

What is EPISD Coronado High School, Bldg. A, Custodial and Book Storage?

EPISD Coronado High School, Bldg. A, Custodial and Book Storage is a renovation/alteration project at 100 Champions Place in El Paso, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New custodial and book room storage, 95 SF / each

Is EPISD Coronado High School, Bldg. A, Custodial and Book Storage open in El Paso?

Construction on EPISD Coronado High School, Bldg. A, Custodial and Book Storage is complete — TDLR records show the project passed its required accessibility inspection in Apr 2025. The building is finished and very likely open.

Where is EPISD Coronado High School, Bldg. A, Custodial and Book Storage located?

EPISD Coronado High School, Bldg. A, Custodial and Book Storage is located at 100 Champions Place, El Paso, TX, 79912, in El Paso County.

Who is the owner or developer of EPISD Coronado High School, Bldg. A, Custodial and Book Storage?

El Paso Independent School District is the property owner/developer of record for EPISD Coronado High School, Bldg. A, Custodial and Book Storage, per its TDLR project registration.

Who is the architect or design firm for EPISD Coronado High School, Bldg. A, Custodial and Book Storage?

Carl Daniel Architects is the design firm of record for EPISD Coronado High School, Bldg. A, Custodial and Book Storage, according to its TDLR filing.

How much does EPISD Coronado High School, Bldg. A, Custodial and Book Storage cost and how big is it?

EPISD Coronado High School, Bldg. A, Custodial and Book Storage has an estimated construction value of $51K and approximately 190 square feet (about $268/sqft), based on its TDLR filing.

Scope of Work

New custodial and book room storage, 95 SF / each

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

100 Champions Place, El Paso, TX, 79912

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 79912 (El Paso)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.