Project intelligenceTDLR TABS2025017554Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Hays CISD | Hays High School 2025 Additions and Renovations in Buda, TX

4800 Jack C Hays Trail, Buda, TX, 78610

Opening ~Apr 2027Review Complete

Hays CISD | Hays High School 2025 Additions and Renovations is a renovation/alteration project at 4800 Jack C Hays Trail, Buda, in Williamson County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Apr 2027. The project has an estimated value of $40.4M across about 109,461 sq ft.

Estimated project value
$40.4M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
109,461 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$369/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 8mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 25, 2025735 days across supplied datesApr 30, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    135 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    600 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Hays CISD | Hays High School 2025 Additions and Renovations

Hays CISD | Hays High School 2025 Additions and Renovations is a $40,360,000 renovation and alteration project located at 4800 Jack C Hays Trail in Buda, Texas. The scope covers 109,461 sq ft of work, representing a significant expansion and upgrade to the existing facility. This large-scale initiative is part of a broader capital improvement effort for the district's secondary schools.

The project was registered with TDLR in April 2025, with plan review completed in the same month. Construction is scheduled to begin in September 2025 and is scheduled to finish in April 2027. This two-year build window is substantially longer than the median 92-day schedule for similar renovation filings in Williamson County, reflecting the complexity of working within an active educational environment.

Design and Funding Context

Huckabee serves as the design firm of record for this project. The estimated cost of $369 per square foot is above the county median of $95 per square foot for renovation and alteration work. This premium reflects the specialized nature of high school facilities, which require robust infrastructure, safety systems, and modern learning environments. The project utilizes public funds, consistent with its status as a district-owned asset.

Hays CISD has six other TDLR-registered projects on record, totaling nearly $500 million. These include a new high school in Buda and renovations at Lehman and Johnson High Schools. This project fits within a pattern of significant investment in the district's infrastructure.

Local Market Position

The construction activity in Buda is part of a broader trend in Williamson County, where 709 renovation and alteration projects were registered in the last 24 months. While the median cost for these filings is $250,000, this project’s scale places it in the top quarter of estimated costs for its type. The local area, characterized by a median household income of $110,417 and a median home value of $379,300, supports a robust construction labor market. Williamson County’s unemployment rate was 4.2 percent in June 2026, a figure that has risen from the previous year, indicating a shifting labor landscape for the trades involved in this build.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78610 (Buda)

One email per change. Unsubscribe in one click. Privacy.

Hays CISD | Hays High School 2025 Additions and Renovations is a Renovation/Alteration project located at 4800 Jack C Hays Trail, Buda, TX 78610 in Buda, Texas. The project has an estimated value of $40.4M covering 109,461 sq ft. Hays CISD is the property owner and Huckabee is the design firm of record. The project was registered with TDLR on April 25, 2025.

Frequently Asked Questions

When is construction scheduled to finish?

The project is scheduled to finish in April 2027. Construction is set to start in September 2025, following the completion of plan review in April 2025.

Who is the design firm for this project?

Huckabee is the design firm of record for the Hays High School additions and renovations. They are responsible for the architectural and engineering aspects of the $40.3 million project.

What is the total square footage of the work?

The filing lists 109,461 sq ft of work. This figure represents the scope of the renovation and additions planned for the Hays High School facility in Buda.

Is the project located in a flood zone?

It is classified as Zone X, which indicates a lower risk of flooding compared to designated flood zones.

How does this project compare to other local renovations?

The estimated cost of $369 per square foot is above the Williamson County median of $95 per square foot. The 600-day build window is also longer than the county median of 92 days for similar filings.

What is Hays CISD | Hays High School 2025 Additions and Renovations?

Hays CISD | Hays High School 2025 Additions and Renovations is a renovation/alteration project at 4800 Jack C Hays Trail in Buda, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Hays CISD | Hays High School 2025 Additions and Renovations

Is Hays CISD | Hays High School 2025 Additions and Renovations open in Buda?

Hays CISD | Hays High School 2025 Additions and Renovations is still under construction in Buda, TX, with an estimated completion of Apr 2027 according to its TDLR registration.

Where is Hays CISD | Hays High School 2025 Additions and Renovations located?

Hays CISD | Hays High School 2025 Additions and Renovations is located at 4800 Jack C Hays Trail, Buda, TX, 78610, in Williamson County.

Who is the owner or developer of Hays CISD | Hays High School 2025 Additions and Renovations?

Hays CISD is the property owner/developer of record for Hays CISD | Hays High School 2025 Additions and Renovations, per its TDLR project registration.

Who is the architect or design firm for Hays CISD | Hays High School 2025 Additions and Renovations?

Huckabee is the design firm of record for Hays CISD | Hays High School 2025 Additions and Renovations, according to its TDLR filing.

How much does Hays CISD | Hays High School 2025 Additions and Renovations cost and how big is it?

Hays CISD | Hays High School 2025 Additions and Renovations has an estimated construction value of $40.4M and approximately 109,461 square feet (about $369/sqft), based on its TDLR filing.

Scope of Work

Hays CISD | Hays High School 2025 Additions and Renovations

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

4800 Jack C Hays Trail, Buda, TX, 78610

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Related City Permits

Building permits found at or near this location

4800 SAGE HEN DR

Homeowner has a Stab Lock panel that needs replacing. Ill be replacing the main and sub panel with a Austin Energy approved panel.

ActiveElectrical PermitUpgradeOct 2026
View Details
2026-130347 EP
Happy Watts Electric LLC
4800 BURNET RD BLDG D UNIT 450

Cinque Terre West ATX EAST ELEVATION

FinalElectrical PermitWallOct 2026
View Details
2026-119010 EP
CNV Electrical LLC
4800 BRIDWELL LN

irrigation install

FinalPlumbing PermitIrrigationOct 2026
View Details
2026-128528 PP
4800 CRAIG DR

(Coutin Steven) - INSTALLATION OF CIRCUIT FOR ELEC. VEHICLE CHARGING STATION - ESIP

FinalElectrical PermitSpecial Inspections ProgramSep 2026
View Details
2026-125832 EP
SMART CHARGE RESIDENTAL LLC
4800 MONDONEDO CV

Install new roof-mounted solar system and energy storage system to existing single family residence. Underground AE

ActiveElectrical PermitAuxiliary PowerSep 2026
View Details
2026-091674 EP
Tesla Energy Operations, Inc.

Watch all construction in 78610 (Buda)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.