A New Buiding Shell Addition

3418 Memorial Drive, Waco, TX 76711, Waco, TX, 76711
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025018533
$80K
Project Value
1,030
Square Feet
$78/sqft
Cost/SqFt
7 months
Duration
Registered:May 8, 2025
Start:Jun 16, 2025
Target:Dec 31, 2025
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Shell building addition to an existing Fire Department space for the City of Beverly Hills.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 8, 2025
Review Complete
+281d
May 8, 2025
Inspection Complete
February 13, 2026
Construction Start
June 16, 2025
Expected Completion
December 31, 2025