Project intelligenceTDLR TABS2025018939Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Shaver Phase II Allendale Road to Vince Bayou Bridge in Pasadena, TX

Shaver Street, Allendale Road to Vince Bayou Brid, Pasadena, TX, 77506

Opening ~Feb 2027Review Complete

Shaver Phase II Allendale Road to Vince Bayou Bridge is a renovation/alteration project at Shaver Street, Allendale Road to Vince Bayou Brid, Pasadena, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Feb 2027. The project has an estimated value of $10.5M across about 272,000 sq ft.

Estimated project value
$10.5M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
272,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$39/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 6mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

May 14, 2025650 days across supplied datesFeb 23, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    110 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    540 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Shaver Phase II Allendale Road to Vince Bayou Bridge

The Shaver Phase II Allendale Road to Vince Bayou Bridge project involves the reconstruction of Shaver Street from Allendale Road to the Vince Bayou Bridge. This 272,000 sq ft renovation and alteration effort in the Vince Heights area of Pasadena is valued at $10,500,000. The project is scheduled to finish in February 2027, with construction work beginning in September 2025.

Scope and Design

The filing details the installation of 10-inch concrete pavement, replacement of water and sanitary sewer lines, and new storm sewer systems. The scope also includes ADA-compliant sidewalks, driveway replacements, and tree work. BinkleyBarfield | DCCM serves as the design firm of record, while Kathy S Rodriguez is the registered accessibility specialist. The project involves public funds and public land, classifying it as a Federally funded roadway project under TDLR registration.

In Harris County, the median estimated cost for similar renovation and alteration filings is $250,000. This Shaver Phase II project sits well above that median, placing it in the top quarter of comparable filings. The scheduled build window of 540 days is longer than the county median of 92 days, reflecting the complexity of the full street reconstruction. At $39 per square foot, the cost per unit area is below the county median of $80 per square foot.

The City of Pasadena has six other TDLR-registered projects totaling $19,881,076 in the region, including work on Perez Road and Cleveland Street. BinkleyBarfield | DCCM has previously completed other projects in Pasadena, such as a $11,400,000 Shaver Street project and a $1,680,000 Davis Street project. The area profile for ZIP 77506 indicates a population of about 35,243, with a median household income of $50,045 and a median owner-occupied home value of $131,800.

TDLR completed plan review in May 2025, and the status is marked as Review Complete. The project is one of 5,386 registered in Harris County in the last 24 months. Businesses nearby include Best Wireless & Repairs, Sotos Auto Glass, and Supermercados Teloloapan # 6. The Harris County unemployment rate was 5 percent in August 2026, lower than a year earlier. This infrastructure investment aims to improve safety and accessibility for residents and commuters in the Vince Heights neighborhood.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77506 (Pasadena)

One email per change. Unsubscribe in one click. Privacy.

Shaver Phase II Allendale Road to Vince Bayou Bridge is a Renovation/Alteration project located at Shaver Street, Allendale Road to Vince Bayou Brid, Pasadena, TX 77506 in Pasadena, Texas. The project has an estimated value of $10.5M covering 272,000 sq ft. City of Pasadena is the property owner and BinkleyBarfield | DCCM is the design firm of record. The project was registered with TDLR on May 14, 2025.

Frequently Asked Questions

When is the Shaver Phase II construction scheduled to finish?

The project is scheduled to finish in February 2027. Construction is set to start in September 2025, following the completion of plan review by TDLR in May 2025.

Who is the owner of this roadway project?

The City of Pasadena is the owner and developer of record for this renovation and alteration project on Shaver Street in Pasadena, Texas.

What is included in the scope of work?

The scope includes 10-inch concrete pavement, storm sewer, water line replacement, sanitary sewer, ADA-compliant sidewalks, driveway replacements, and tree work.

Is the new Shaver Street section open to traffic?

The project is in the construction phase, starting in September 2025. The filing does not indicate that the business or roadway is open or operating.

Who is the design firm for this project?

BinkleyBarfield | DCCM is the design firm of record for the Shaver Phase II Allendale Road to Vince Bayou Bridge project in Pasadena, Texas.

What is Shaver Phase II Allendale Road to Vince Bayou Bridge?

Shaver Phase II Allendale Road to Vince Bayou Bridge is a renovation/alteration project at Shaver Street, Allendale Road to Vince Bayou Brid in Pasadena, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Reconstruction of Shaver Street from Allendale Road to the Vince Bayou Bridge of 10" concrete pavement, storm sewer, water line replacement, sanitary sewer, ADA compliant sidewalk, driveway replacements, and trees.

Is Shaver Phase II Allendale Road to Vince Bayou Bridge open in Pasadena?

Shaver Phase II Allendale Road to Vince Bayou Bridge is still under construction in Pasadena, TX, with an estimated completion of Feb 2027 according to its TDLR registration.

Where is Shaver Phase II Allendale Road to Vince Bayou Bridge located?

Shaver Phase II Allendale Road to Vince Bayou Bridge is located at Shaver Street, Allendale Road to Vince Bayou Brid, Pasadena, TX, 77506, in Harris County.

Who is the owner or developer of Shaver Phase II Allendale Road to Vince Bayou Bridge?

City of Pasadena is the property owner/developer of record for Shaver Phase II Allendale Road to Vince Bayou Bridge, per its TDLR project registration.

Who is the architect or design firm for Shaver Phase II Allendale Road to Vince Bayou Bridge?

BinkleyBarfield | DCCM is the design firm of record for Shaver Phase II Allendale Road to Vince Bayou Bridge, according to its TDLR filing.

How much does Shaver Phase II Allendale Road to Vince Bayou Bridge cost and how big is it?

Shaver Phase II Allendale Road to Vince Bayou Bridge has an estimated construction value of $10.5M and approximately 272,000 square feet (about $39/sqft), based on its TDLR filing.

Scope of Work

Reconstruction of Shaver Street from Allendale Road to the Vince Bayou Bridge of 10" concrete pavement, storm sewer, water line replacement, sanitary sewer, ADA compliant sidewalk, driveway replacements, and trees.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Shaver Street, Allendale Road to Vince Bayou Brid, Pasadena, TX, 77506

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 77506 (Pasadena)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Pasadena?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.