DFW EV'S in Dallas, TX

Various Locations in the DFW area, Dallas, TX, 75067

Target date passed (Oct 2026)Review Complete

DFW EV'S is a additions to existing building project at Various Locations in the DFW area, Dallas, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Oct 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $21.0M across about 22,000 sq ft.

Estimated project value
$21.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
22,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$955/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 2mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jun 23, 2025495 days across supplied datesOct 31, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    63 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    432 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About DFW EV'S

Walmart Dallas: EV Charging Install Planned

Walmart is undertaking a significant infrastructure upgrade at various locations in the Dallas area, with a primary filing address in Dallas, TX 75067. The project, identified on the TDLR filing as DFW Ev's, involves installing various EV charging stations within an existing commercial parking lot. This addition to an existing building covers a scope of 22,000 sq ft and carries an estimated cost of $21,000,000. The registered accessibility specialist for this filing is George A Patterson, and the design firm of record is Kimley-Horn and Associates, Inc.

TDLR completed plan review in June 2025 and construction is scheduled to finish in October 2026, with work starting August 2025. The project is privately funded, on private land for private use. The cost per square foot for this installation is $955. This figure is well above the county median of $161 per sq ft for additions to existing buildings in Dallas County. The total estimated cost of $21,000,000 is also above the county median for this type of work, which sits at $638,947.

The owner and developer of record is Walmart Real Estate Bus Trst. This entity has three other TDLR-registered projects totaling $4,800,000. These include a Walmart in Mesquite with a review complete status, and two closed projects in Mckinney and Murphy, each valued at $2,000,000. The involvement of Kimley-Horn and Associates, Inc. links this project to six other filings totaling $7,223,570, including fuel centers and park renovations across Texas.

For the ZIP code 75067, U.S. Census ACS 2023 five-year estimates indicate a population of about 68,451 and a median household income of $76,630. There are 28,990 housing units in the area, with a median owner-occupied home value of $321,100. Housing in this zone is mostly renter-occupied. Other registered projects in the immediate vicinity include renovations at 200 South Mill Street in Lewisville and several QuikTrip locations.

The Dallas County unemployment rate was 3 percent in August 2026, which is lower than a year earlier. This project represents a substantial investment in commercial infrastructure, distinct from the typical renovation filings seen in the region. The TDLR status is listed as Review Complete, confirming the regulatory pathway is established for the upcoming construction phase.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75067 (Dallas)

One email per change. Unsubscribe in one click. Privacy.

DFW EV'S is a Additions to Existing Building project located at Various Locations in the DFW area, Dallas, TX 75067 in Dallas, Texas. The project has an estimated value of $21.0M covering 22,000 sq ft. Walmart Real Estate Bus Trst. is the property owner and Kimley-Horn and Associates, Inc is the design firm of record. The project was registered with TDLR on June 23, 2025.

Frequently Asked Questions

Is the Walmart EV charging station project open?

The TDLR record covers construction only and does not record whether the business has started serving customers. The project is scheduled to finish in October 2026, with construction starting in August 2025.

Who is the owner of this project?

The owner and developer of record is Walmart Real Estate Bus Trst. This entity has other registered projects in Mesquite, Mckinney, and Murphy.

What is the estimated cost of the project?

The estimated cost is $21,000,000. This covers 22,000 sq ft of work, resulting in a cost per sq ft of $955.

Who is the design firm?

Kimley-Horn and Associates, Inc is the design firm of record. They have worked on six other TDLR-registered projects totaling $7,223,570.

What is DFW EV'S?

DFW EV'S is a additions to existing building project at Various Locations in the DFW area in Dallas, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Installing various EV charging stations in an existing commercial parking lot.

Is DFW EV'S open in Dallas?

DFW EV'S was scheduled to finish construction in Oct 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is DFW EV'S located?

DFW EV'S is located at Various Locations in the DFW area, Dallas, TX, 75067, in Dallas County.

Who is the owner or developer of DFW EV'S?

Walmart Real Estate Bus Trst. is the property owner/developer of record for DFW EV'S, per its TDLR project registration.

Who is the architect or design firm for DFW EV'S?

Kimley-Horn and Associates, Inc is the design firm of record for DFW EV'S, according to its TDLR filing.

How much does DFW EV'S cost and how big is it?

DFW EV'S has an estimated construction value of $21.0M and approximately 22,000 square feet (about $955/sqft), based on its TDLR filing.

Scope of Work

Installing various EV charging stations in an existing commercial parking lot.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Various Locations in the DFW area, Dallas, TX, 75067

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 75067 (Dallas)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.