Project intelligenceTDLR TABS2025022525Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Moonshot Project Serna Elementary School in San Antonio, TX

2569 N.E. Loop 410, San Antonio, TX, 78217

Construction complete · Sep 2026Inspection Complete

Moonshot Project Serna Elementary School is a renovation/alteration project at 2569 N.E. Loop 410, San Antonio, in Bexar County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $120K across about 1,502 sq ft.

Estimated project value
$120K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
1,502 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$80/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
29 days
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jul 1, 2025436 days across supplied datesSep 10, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    9 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    29 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    398 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Moonshot Project Serna Elementary School

Moonshot Project Serna Elementary School is complete. Located at 2569 N.E. Loop 410 in San Antonio, this renovation converted two existing classrooms into one larger space for a new educational program. The building passed its final TDLR accessibility inspection in September 2026, confirming the work is finished.

The project involved an interior alteration covering 1,502 square feet with an estimated cost of $120,000. This equals $80 per square foot. This cost is below the Bexar County median for similar renovation filings, which stands at $250,000. The scheduled build window was 29 days, shorter than the county median of 103 days.

Project Details

North East Independent School District served as the owner of record. DeMunbrun Scarnato Associates, Inc. was the design firm of record, and Stephen A Meyer acted as the registered accessibility specialist. The project involved public funds and public land. Plan review was completed in July 2025, and construction began that same month. The filing listed an anticipated completion date of August 2025, though the final inspection occurred in September 2026.

North East Independent School District has six other TDLR-registered projects totaling $2,643,000. These include facilities such as Royal Ridge Elementary School and the NEISD School Nutrition Services Warehouse. DeMunbrun Scarnato Associates, Inc. also has six other registered projects totaling $2,430,000, including work on Driscoll Middle School and The Cranky Pickle in New Braunfels.

The site is in the San Antonio International Airport Vicinity. Nearby businesses include The Palace Men's Club, Worldwide Clinical Trials, and Cedra Clinical Research LLC. According to U.S. Census American Community Survey five-year estimates for ZIP code 78217, the population is about 33,959. The median household income is $56,852, and the median owner-occupied home value is $216,100. Housing in this area is an even mix of owner- and renter-occupied.

Bexar County unemployment was 4.6 percent in August 2026, lower than a year earlier. This project represents a specific interior improvement within an existing school structure rather than a new construction. The scope was limited to the interior renovation of the two classrooms mentioned in the filing. No other structural changes are detailed in the provided facts.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78217 (San Antonio)

One email per change. Unsubscribe in one click. Privacy.

Moonshot Project Serna Elementary School is a Renovation/Alteration project located at 2569 N.E. Loop 410, San Antonio, TX 78217 in San Antonio, Texas. The project has an estimated value of $120K covering 1,502 sq ft. North East Independent School District is the property owner and DeMunbrun Scarnato Associates, Inc. is the design firm of record. The project was registered with TDLR on July 1, 2025.

Frequently Asked Questions

Is the Serna Elementary classroom renovation finished?

Yes, the project passed its final TDLR accessibility inspection in September 2026. The construction is complete, and the status is marked as Inspection Complete.

What was the cost of the Serna Elementary renovation?

The estimated cost for the project was $120,000. This figure covers the interior renovation of two existing classrooms to create one larger classroom.

Who designed the Serna Elementary classroom conversion?

DeMunbrun Scarnato Associates, Inc. was the design firm of record for this project. Stephen A Meyer served as the registered accessibility specialist.

Where is the Serna Elementary School located?

The school is located at 2569 N.E. Loop 410 in San Antonio, Texas. It is situated in Bexar County near the San Antonio International Airport.

How much square footage did the renovation cover?

The renovation covered 1,502 square feet. This area was converted from two existing classrooms into a single larger classroom for a new educational program.

What is Moonshot Project Serna Elementary School?

Moonshot Project Serna Elementary School is a renovation/alteration project at 2569 N.E. Loop 410 in San Antonio, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Interior renovation of two existing classrooms to convert them to one larger classroom for a new educational program.

Is Moonshot Project Serna Elementary School open in San Antonio?

Construction on Moonshot Project Serna Elementary School is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.

Where is Moonshot Project Serna Elementary School located?

Moonshot Project Serna Elementary School is located at 2569 N.E. Loop 410, San Antonio, TX, 78217, in Bexar County.

Who is the owner or developer of Moonshot Project Serna Elementary School?

North East Independent School District is the property owner/developer of record for Moonshot Project Serna Elementary School, per its TDLR project registration.

Who is the architect or design firm for Moonshot Project Serna Elementary School?

DeMunbrun Scarnato Associates, Inc. is the design firm of record for Moonshot Project Serna Elementary School, according to its TDLR filing.

How much does Moonshot Project Serna Elementary School cost and how big is it?

Moonshot Project Serna Elementary School has an estimated construction value of $120K and approximately 1,502 square feet (about $80/sqft), based on its TDLR filing.

Scope of Work

Interior renovation of two existing classrooms to convert them to one larger classroom for a new educational program.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

2569 N.E. Loop 410, San Antonio, TX, 78217

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78217 (San Antonio)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in San Antonio?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.