Target date passed (Aug 2026)Review Complete

LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway is a new construction project at Near 21103 State Hwy 71, Spicewood, in Travis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Aug 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $53K across about 6,500 sq ft.

Estimated project value
$53K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
6,500 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$8/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 2mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jun 15, 2025426 days across supplied datesAug 15, 2026

4 timeline dates shown.

  1. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR filing

    View source record
  2. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    115 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    311 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway

N/A - Private drive and public road is a new construction project by Lake Travis ISD near 21103 State Hwy 71 in Spicewood, Texas. The scope covers 6,500 square feet of sidewalk and curb ramps with an estimated cost of $53,000. Construction was scheduled to start in June 2025, with completion targeted for August 2026.

Project Scope and Design

Malone Wheeler, Inc. serves as the design firm of record for this accessibility project. Kathy Ann Riley is the registered accessibility specialist listed in the TDLR filing. The estimated cost of $53,000 translates to approximately $8 per square foot, a figure that is below the county median of $125 per square foot for similar new construction filings in Travis County.

The project involves public funds, public land, or a Federally funded roadway project. TDLR completed plan review in October 2025. Construction was scheduled to finish in August 2026; however, TDLR has not yet recorded a final inspection, so the current state of the site is not confirmed in the public record.

Regional Context

Lake Travis ISD holds six other TDLR-registered projects totaling $103,646,000, including the Lake Travis High School Annex and the Educational Development Center. Malone Wheeler, Inc. has four other registered projects totaling $15,800,000, such as the Lake Travis High School project in Austin. The scheduled build window for this Spicewood project is 426 days, which is longer than the county median of 304 days for new construction filings.

Spicewood is located in Travis County, with a ZIP code 78669 population of about 11,980 according to U.S. Census ACS 2023 five-year estimates. The median household income in the area is $126,422, and the median owner-occupied home value is $576,200. Other registered projects in the same area include the Lake Travis Community Library West renovation and the HWY 71 Car Club new construction. The Travis County unemployment rate was 3.9 percent in July 2026, according to FRED data.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78669 (Spicewood)

One email per change. Unsubscribe in one click. Privacy.

LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway is a New Construction project located at Near 21103 State Hwy 71, Spicewood, TX 78669 in Spicewood, Texas. The project has an estimated value of $53K covering 6,500 sq ft. Lake Travis ISD is the property owner and Malone Wheeler, Inc is the design firm of record. The project was registered with TDLR on October 8, 2025.

Frequently Asked Questions

Is the sidewalk project in Spicewood complete?

TDLR has not yet recorded a final inspection for this project. While construction was scheduled to finish in August 2026, the public record does not confirm the site's current status.

Who is building the sidewalk near State Hwy 71?

Lake Travis ISD is the owner of record. Malone Wheeler, Inc. is the design firm, and Kathy Ann Riley is the registered accessibility specialist listed in the TDLR filing.

How much does the Spicewood sidewalk project cost?

The estimated cost for the 6,500 square feet of sidewalk and curb ramps is $53,000. This equates to approximately $8 per square foot, which is below the Travis County median for similar filings.

What is the scope of the work?

The filing specifies 6,500 square feet of new sidewalk and curb ramps. The project involves new construction on public land or a Federally funded roadway near 21103 State Hwy 71.

When did TDLR review the plans?

TDLR completed plan review in October 2025. Construction was scheduled to start in June 2025, with a target completion date of August 2026.

What is LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway?

LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway is a new construction project at Near 21103 State Hwy 71 in Spicewood, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: 6,500 SF of sidewalk and curb ramps

Is LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway open in Spicewood?

LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway was scheduled to finish construction in Aug 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway located?

LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway is located at Near 21103 State Hwy 71, Spicewood, TX, 78669, in Travis County.

Who is the owner or developer of LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway?

Lake Travis ISD is the property owner/developer of record for LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway, per its TDLR project registration.

Who is the architect or design firm for LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway?

Malone Wheeler, Inc is the design firm of record for LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway, according to its TDLR filing.

How much does LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway cost and how big is it?

LTISD Educational Facilities Campus - Phase 1 - Private Drive & Reimers-Peacock Public Roadway has an estimated construction value of $53K and approximately 6,500 square feet (about $8/sqft), based on its TDLR filing.

Scope of Work

6,500 SF of sidewalk and curb ramps

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Near 21103 State Hwy 71, Spicewood, TX, 78669

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78669 (Spicewood)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Spicewood?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.