635 Exchange Spec Suite - Bldg C

11641 Newberry St, Dallas, TX, 75238

Target date passed (Jul 2026)Review Complete

635 Exchange Spec Suite - Bldg C is a renovation/alteration project at 11641 Newberry St, Dallas, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Jul 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $455K across about 3,311 sq ft.

Estimated project value
$455K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
3,311 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$137/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
6 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 13, 2025275 days across supplied datesJul 15, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    107 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    42 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    126 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About 635 Exchange Spec Suite - Bldg C

The 635 Exchange Building C project involves the renovation of a 3,311 square foot spec office suite located at 11641 Newberry St in Dallas. Filed under the name 635 Exchange Spec Suite - Bldg C, this alteration converts warehouse space into a functional office environment. The estimated cost for this work is $454,500, which calculates to $137 per square foot. This figure sits above the Dallas County median of $72 per square foot for similar renovation filings.

The scope of work includes office space, a conference room, workspace, a janitor closet, an IT closet, and four restrooms. The owner of record is PR III CRE 635 Exchange Owner, who also registered two other projects at this location: 635 Exchange Building A and 635 Exchange Building B. Both of those projects have completed review, while this current filing for Building C remains in the review complete stage with construction pending final verification.

LGE DesignBuild serves as the design firm of record for this project. The firm has registered six other projects totaling over $32 million, including work in Arlington and other Dallas locations. The registered accessibility specialist for this specific filing is Jeffery L Kelley. The project is privately funded and situated on private land for private use, distinct from municipal or public infrastructure projects.

TDLR completed the plan review process in March 2026. Construction was scheduled to begin in January 2026 and finish in July 2026. The scheduled build window of 168 days is longer than the county median of 92 days for renovation and alteration projects. Despite the completion date having passed, TDLR has not yet recorded a final inspection. Therefore, the current state of the site is not confirmed in the public record, and the project's completion status remains unverified by the state agency.

The surrounding area, ZIP code 75238, has a population of approximately 33,439 people according to U.S. Census estimates. The median household income is $75,498, and the median owner-occupied home value is $526,100. Housing in this area is an even mix of owner- and renter-occupied units. Dallas County's unemployment rate stood at 3.3 percent in July 2026, slightly higher than the previous year, providing context for the local labor market during this construction period.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75238 (Dallas)

One email per change. Unsubscribe in one click. Privacy.

635 Exchange Spec Suite - Bldg C is a Renovation/Alteration project located at 11641 Newberry St, Dallas, TX 75238 in Dallas, Texas. The project has an estimated value of $455K covering 3,311 sq ft. PR III CRE 635 Exchange Owner is the property owner and LGE DesignBuild is the design firm of record. The project was registered with TDLR on October 13, 2025.

Frequently Asked Questions

Is the 635 Exchange Building C renovation finished?

TDLR completed plan review in March 2026 and construction was scheduled to finish in July 2026. However, TDLR has not yet recorded a final inspection, so the completion status is not confirmed in the public record.

What is the address of the 635 Exchange Building C project?

The project is located at 11641 Newberry St, Dallas, TX 75238. It is a 3,311 square foot spec office suite within a warehouse building.

Who is the design firm for this project?

LGE DesignBuild is the design firm of record. They have registered six other projects totaling over $32 million, including work in Arlington and other Dallas locations.

How much does the renovation cost per square foot?

The estimated cost is $454,500 for 3,311 square feet, resulting in a cost of $137 per square foot. This is above the Dallas County median of $72 per square foot for similar filings.

What is 635 Exchange Spec Suite - Bldg C?

635 Exchange Spec Suite - Bldg C is a renovation/alteration project at 11641 Newberry St in Dallas, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: This project consists of a 3.311 SF Spec Office located in a warehouse building. The project consists of office space, conference room, workspace, janitor closet, IT closet, and (4) restrooms.

Is 635 Exchange Spec Suite - Bldg C open in Dallas?

635 Exchange Spec Suite - Bldg C was scheduled to finish construction in Jul 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is 635 Exchange Spec Suite - Bldg C located?

635 Exchange Spec Suite - Bldg C is located at 11641 Newberry St, Dallas, TX, 75238, in Dallas County.

Who is the owner or developer of 635 Exchange Spec Suite - Bldg C?

PR III CRE 635 Exchange Owner is the property owner/developer of record for 635 Exchange Spec Suite - Bldg C, per its TDLR project registration.

Who is the architect or design firm for 635 Exchange Spec Suite - Bldg C?

LGE DesignBuild is the design firm of record for 635 Exchange Spec Suite - Bldg C, according to its TDLR filing.

How much does 635 Exchange Spec Suite - Bldg C cost and how big is it?

635 Exchange Spec Suite - Bldg C has an estimated construction value of $455K and approximately 3,311 square feet (about $137/sqft), based on its TDLR filing.

Scope of Work

This project consists of a 3.311 SF Spec Office located in a warehouse building. The project consists of office space, conference room, workspace, janitor closet, IT closet, and (4) restrooms.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

11641 Newberry St, Dallas, TX, 75238

Location by street address

Watch all construction in 75238 (Dallas)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.