๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
SH 5 (Shared Use Path)
From: Newport Drive To: Umphress Street, Van Alstyne, TX, 75495
Construction50%
๐Project Metrics
TDLR #TABS2026003899$1.5M
Project Value
32,655
Square Feet
$46/sqft
Cost/SqFt
6 months
Duration
Registered:Oct 21, 2025
Start:Aug 1, 2026
Target:Jan 27, 2027
Remaining:339 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construct 10' wide shared use path including curb ramps, drainage structures, driveway reconstruction, signing and pavement markings.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 21, 2025
Review Complete
October 21, 2025
Construction Start
August 1, 2026
Expected Completion
January 27, 2027
๐Related Projects
๐คSame Owner
$4.6M total๐Nearby Projects
Within 1 kmVan Alstyne Public Safety
820 N. Waco Streetยท$23.0M
Van Alstyne Umpress/HYNDS 24-Acre Park
Block between Kelly Lane & S dallas Ave,, Van Alstyne, TX 75495ยท$5.8M
Workshop and Retail Sales for Modern Root
306 S. Waco St., Van Alstyne, TX 75495ยท$500K
WAREHOUSE DEVELOPMENT FOR FORCED PERFORMANCE
601 MARTIN DUKE RD., Van Alstyne, TX 75495ยท$1.3M
Property Owner
๐ค
TxDOT District: Paris
Contact: Duane Good, P.E.
4 projects ยท $4.6M
View company profile
1365 N. Main Street, Paris, Texas 75460
Design Firm
๐๏ธ
LJA Engineering, Inc.
4 projects ยท $80.7M
View company profile
2700 La Frontera, Suite 200, Round Rock, Texas 78681