Port Isabel Lighthouse Keeper's Cottage and Restroom Renovation

423 E. Queen Isabella Blvd, Port Isabel, TX 78578, Port Isabel, TX, 78578
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026008204
$400K
Project Value
851
Square Feet
$470/sqft
Cost/SqFt
10 months
Duration
Registered:Dec 16, 2025
Start:Dec 22, 2025
Target:Oct 30, 2026
Remaining:250 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Renovation of existing Keeper's Cottage and Restooms

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
+37d
December 16, 2025
Review Complete
January 22, 2026
Construction Start
December 22, 2025
Expected Completion
October 30, 2026