Project intelligenceTDLR TABS2026011339New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

East Cliff Elementary Playground in Portland, TX

1140 W. Broadway Blvd., Portland, TX, 78374

Target date passed (Aug 2026)Review Complete

East Cliff Elementary Playground is a new construction project at 1140 W. Broadway Blvd., Portland, in San Patricio County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Aug 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $2.0M across about 6,000 sq ft.

Estimated project value
$2.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
6,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$333/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
5 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jan 30, 2026188 days across supplied datesAug 6, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    30 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    153 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    5 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About East Cliff Elementary Playground

East Cliff Elementary Playground adds a new 6,000 sq ft facility at 1140 W. Broadway Blvd. in Portland, Texas. The project is a New Construction effort by Gregory-Portland Independent School District with an estimated cost of $2,000,000. This equates to $333 per square foot, a figure that sits above the San Patricio County median of $200 for similar new construction filings.

Project Scope and Timeline

The scope of work is defined strictly as a new 6,000 SF Playground. Construction was scheduled to begin in March 2026, with a planned completion date of August 2026. The scheduled build window of 153 days is shorter than the county median of 243 days for comparable projects. TDLR completed plan review in August 2026. However, TDLR has not yet recorded a final inspection, so the current state of the site is not confirmed in the public record.

Gregory-Portland Independent School District is the owner of record for this project. The district has six other TDLR-registered projects in the area, including G-PISD High School - Building C and Food & Nutrition Services. This new playground filing is part of a broader pattern of infrastructure development within the district. The project involves public funds and public land, consistent with school district operations in San Patricio County.

Local Context and Costs

The estimated cost of $2,000,000 is above the county median of $1,100,000 for new construction projects in San Patricio County. The middle half of costs for these projects ranges from $450,000 to $3,300,000. The size of this playground, at 6,000 sq ft, is slightly smaller than the county median of 7,652 sq ft. The cost per square foot reflects the specific requirements of accessibility and playground construction standards.

Portland is located in San Patricio County, with a population of about 20,152 according to U.S. Census ACS 2023 five-year estimates for ZIP 78374. The median household income in the area is $81,580. Nearby businesses include Walmart Supercenter and various retail services. The San Patricio County unemployment rate was 5.4 percent in July 2026, higher than a year earlier. This project contributes to the local construction activity and infrastructure development in the region.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78374 (Portland)

One email per change. Unsubscribe in one click. Privacy.

East Cliff Elementary Playground is a New Construction project located at 1140 W. Broadway Blvd., Portland, TX 78374 in Portland, Texas. The project has an estimated value of $2.0M covering 6,000 sq ft. Gregory-Portland Independent School District is the property owner. The project was registered with TDLR on January 30, 2026.

Frequently Asked Questions

Is East Cliff Elementary Playground open?

The TDLR record has not yet recorded a final inspection. Therefore, the current operational status of the site is not confirmed in the public record. Construction was scheduled to finish in August 2026, but final verification is pending.

Who is building the new playground?

Gregory-Portland Independent School District is the owner of record. The registered accessibility specialist for the project is Jose Ricardo Guerrero. The work is classified as New Construction under TDLR filings.

How much does the project cost?

The estimated cost is $2,000,000. This amount is above the San Patricio County median of $1,100,000 for new construction filings. The cost per square foot is $333, which is higher than the county median of $200.

Where is the playground located?

The address is 1140 W. Broadway Blvd., Portland, TX 78374. It is located in San Patricio County. Nearby businesses include Walmart Supercenter and Gregory Portland ISD Board Room.

What is the size of the new playground?

The scope of work is a new 6,000 sq ft Playground. This size is slightly smaller than the county median of 7,652 sq ft for new construction projects in San Patricio County.

What is East Cliff Elementary Playground?

East Cliff Elementary Playground is a new construction project at 1140 W. Broadway Blvd. in Portland, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New 6,000 SF Playground

Is East Cliff Elementary Playground open in Portland?

East Cliff Elementary Playground was scheduled to finish construction in Aug 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is East Cliff Elementary Playground located?

East Cliff Elementary Playground is located at 1140 W. Broadway Blvd., Portland, TX, 78374, in San Patricio County.

Who is the owner or developer of East Cliff Elementary Playground?

Gregory-Portland Independent School District is the property owner/developer of record for East Cliff Elementary Playground, per its TDLR project registration.

How much does East Cliff Elementary Playground cost and how big is it?

East Cliff Elementary Playground has an estimated construction value of $2.0M and approximately 6,000 square feet (about $333/sqft), based on its TDLR filing.

Scope of Work

New 6,000 SF Playground

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

1140 W. Broadway Blvd., Portland, TX, 78374

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78374 (Portland)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Portland?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.