Project intelligenceTDLR TABS2026017171New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521

Chimney Rock Road to FM 521, Fresno, TX, 77545

Opening ~Dec 2027Review Complete

Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 is a new construction project at Chimney Rock Road to FM 521, Fresno, in Fort Bend County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Dec 2027. The project has an estimated value of $20.6M across about 60,000 sq ft.

Estimated project value
$20.6M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
60,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$344/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 6mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 8, 2026602 days across supplied datesDec 1, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    6 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    48 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    548 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77545 (Fresno)

One email per change. Unsubscribe in one click. Privacy.

Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 is a New Construction project located at Chimney Rock Road to FM 521, Fresno, TX 77545 in Fresno, Texas. The project has an estimated value of $20.6M covering 60,000 sq ft. Fort Bend County is the property owner and Bowman Engineering is the design firm of record. The project was registered with TDLR on April 8, 2026.

Frequently Asked Questions

What is Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521?

Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 is a new construction project at Chimney Rock Road to FM 521 in Fresno, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construction of four lane concrete boulevard from Chimney Rock Road to FM 521 (60,000 sq.ft.)

Is Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 open in Fresno?

Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 is still under construction in Fresno, TX, with an estimated completion of Dec 2027 according to its TDLR registration.

Where is Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 located?

Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 is located at Chimney Rock Road to FM 521, Fresno, TX, 77545, in Fort Bend County.

Who is the owner or developer of Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521?

Fort Bend County is the property owner/developer of record for Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521, per its TDLR project registration.

Who is the architect or design firm for Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521?

Bowman Engineering is the design firm of record for Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521, according to its TDLR filing.

How much does Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 cost and how big is it?

Lake Olympia Parkway Extension Segment 2 Chimney Rock to FM 521 has an estimated construction value of $20.6M and approximately 60,000 square feet (about $344/sqft), based on its TDLR filing.

Scope of Work

Construction of four lane concrete boulevard from Chimney Rock Road to FM 521 (60,000 sq.ft.)

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Chimney Rock Road to FM 521, Fresno, TX, 77545

Location by street address

Watch all construction in 77545 (Fresno)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.