Project intelligenceTDLR TABS2026018430Additions to Existing Building
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Grandview ISD 2025 Bond Program

1009 S Carroll St, Grandview, TX, 76050

Opening ~Jul 2027Review Complete

Grandview ISD 2025 Bond Program is a additions to existing building project at 1009 S Carroll St, Grandview, in Johnson County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Jul 2027. The project has an estimated value of $2.0M across about 5,618 sq ft.

Estimated project value
$2.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
5,618 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$356/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1 year
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 23, 2026434 days across supplied datesJul 1, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    58 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    11 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    365 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Grandview ISD 2025 Bond Program

The Metal Shop and Girls Softball Locker Room project at Grandview ISD adds 3,039 square feet to the existing metal shop and constructs a 2,579 square foot field house for the girls' softball team. Located at 1009 S Carroll St in Grandview, Texas, this work totals 5,618 square feet of new construction under the Grandview ISD 2025 Bond Program.

The estimated cost is $2,000,000, equating to $356 per square foot. TDLR registered the project in April 2026 and completed plan review in June 2026. Construction is scheduled to begin in July 2026 and is scheduled to finish in July 2027.

Design and Scope

BWA Architects serves as the design firm of record, with Glenn Thomas Comtois listed as the registered accessibility specialist. Kirby Basham is the owner or developer of record. The project involves public funds and public land. In Johnson County, the median estimated cost for similar additions is $500,000, placing this project above the county median for its type.

The median size for these projects in Johnson County is 6,250 square feet, while this project is 5,618 square feet. The median cost per square foot in the county is $119, making this project's $356 per square foot above the county median. The scheduled build window of 365 days is longer than the county median of 212 days for similar filings.

BWA Architects has six other TDLR-registered projects totaling $34,500,000, including an intermediate school addition in Grandview valued at $10,000,000 and a high school remediation project in Grandview valued at $2,000,000. Both of those projects have review complete status.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76050 (Grandview)

One email per change. Unsubscribe in one click. Privacy.

Grandview ISD 2025 Bond Program is a Additions to Existing Building project located at 1009 S Carroll St, Grandview, TX 76050 in Grandview, Texas. The project has an estimated value of $2.0M covering 5,618 sq ft. Kirby Basham is the property owner and BWA Architects is the design firm of record. The project was registered with TDLR on April 23, 2026.

Frequently Asked Questions

When will the Metal Shop and Girls Softball Locker Room be finished?

Construction is scheduled to finish in July 2027. The project started plan review in June 2026 with construction beginning in July 2026.

Who is designing the new Grandview ISD facilities?

BWA Architects is the design firm of record. Glenn Thomas Comtois is the registered accessibility specialist for the project.

How much does the project cost per square foot?

The estimated cost is $2,000,000 for 5,618 square feet, resulting in a cost of $356 per square foot.

What is the total square footage of the new construction?

The project adds 3,039 square feet to the metal shop and builds a 2,579 square foot field house, totaling 5,618 square feet.

What is Grandview ISD 2025 Bond Program?

Grandview ISD 2025 Bond Program is a additions to existing building project at 1009 S Carroll St in Grandview, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: The project consist of an addition to an existing building and a new build for Grandview ISD Campus. There is approximately 3,039 SF of addition to the metal shop and a 2,579 sf field house for the girl's softball locker room.

Is Grandview ISD 2025 Bond Program open in Grandview?

Grandview ISD 2025 Bond Program is still under construction in Grandview, TX, with an estimated completion of Jul 2027 according to its TDLR registration.

Where is Grandview ISD 2025 Bond Program located?

Grandview ISD 2025 Bond Program is located at 1009 S Carroll St, Grandview, TX, 76050, in Johnson County.

Who is the owner or developer of Grandview ISD 2025 Bond Program?

Kirby Basham is the property owner/developer of record for Grandview ISD 2025 Bond Program, per its TDLR project registration.

Who is the architect or design firm for Grandview ISD 2025 Bond Program?

BWA Architects is the design firm of record for Grandview ISD 2025 Bond Program, according to its TDLR filing.

How much does Grandview ISD 2025 Bond Program cost and how big is it?

Grandview ISD 2025 Bond Program has an estimated construction value of $2.0M and approximately 5,618 square feet (about $356/sqft), based on its TDLR filing.

Scope of Work

The project consist of an addition to an existing building and a new build for Grandview ISD Campus. There is approximately 3,039 SF of addition to the metal shop and a 2,579 sf field house for the girl's softball locker room.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

1009 S Carroll St, Grandview, TX, 76050

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 76050 (Grandview)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.