Project intelligenceTDLR TABS2026021464Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Texas State University: Student Success Commons at Albert B. Alkek Library building in San Marcos, TX

601 University Drive, San Marcos, TX, 78666

Opening ~Dec 2026Review Complete

Texas State University: Student Success Commons at Albert B. Alkek Library building is a renovation/alteration project at 601 University Drive, San Marcos, in Hays County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Dec 2026. The project has an estimated value of $3.5M across about 38,000 sq ft.

Estimated project value
$3.5M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
38,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$92/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
6 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

May 29, 2026200 days across supplied datesDec 15, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    7 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    26 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    167 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Texas State University: Student Success Commons at Albert B. Alkek Library building

Texas State University is renovating approximately 38,000 square feet of the sixth floor at the Albert B. Alkek Library in San Marcos. The project, valued at $3,500,000, transforms this space into the Student Success Commons. Construction started in June 2026 and is scheduled to finish in December 2026. The work is classified as a renovation and alteration of existing interior spaces.

The scope of work includes new staff offices and student group study support spaces. This interior renovation affects a significant portion of the library's upper levels. The project is located at 601 University Drive in Hays County. The estimated cost of $92 per square foot is close to the county median of $95 for similar renovation filings.

Project Details and Timeline

The Lawrence Group is the design firm of record for this project. Martelle Luedecke is the registered accessibility specialist. TDLR completed plan review in July 2026. The scheduled build window is 193 days, which is longer than the county median of 92 days for renovation and alteration projects. The project involves public funds and is registered with TDLR.

Texas State University has six other TDLR-registered projects in San Marcos totaling $20,090,000. These include the Undergraduate Academic Center and the Jones Dining Complex. The Lawrence Group has six other TDLR-registered projects totaling $3,193,000. These locations include Kyle Village North and 8240 Preston Rd. The project is part of a broader pattern of university infrastructure updates in the region.

The estimated cost of $3,500,000 is above the county median for its type, placing it in the top quarter of similar filings. The size of 38,000 square feet is significantly larger than the county median of 3,277 square feet. This project represents a substantial investment in student support facilities. The renovation aims to enhance the learning environment at Alkek Library.

Local Context and Market Data

The ZIP code 78666 has a population of about 87,775 according to U.S. Census ACS 2023 estimates. The median household income is $55,478. There are 36,354 housing units, with a median owner-occupied home value of $271,900. Hays County unemployment rate was 4.1 percent in June 2026, higher than a year earlier. The project is situated in a community with a mix of rental and owner-occupied housing.

Third-party records from ConstructConnect list the project under San Marcos Educational Remodeling. The bid date for related projects is noted as June 18, 2026. The project is identified by the number 6166109 in these records. The TDLR status is Review Complete. The project is not yet operational, and no opening date has been announced.

The renovation of the sixth floor of Alkek Library is a key component of Texas State University's campus improvements. The project focuses on creating dedicated spaces for student collaboration and staff work. The completion of this project will add to the university's infrastructure. The registration with TDLR ensures compliance with accessibility standards. The project is a significant addition to the San Marcos campus.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78666 (San Marcos)

One email per change. Unsubscribe in one click. Privacy.

Texas State University: Student Success Commons at Albert B. Alkek Library building is a Renovation/Alteration project located at 601 University Drive, San Marcos, TX 78666 in San Marcos, Texas. The project has an estimated value of $3.5M covering 38,000 sq ft. Texas State University is the property owner and Lawrence Group is the design firm of record. The project was registered with TDLR on May 29, 2026.

Frequently Asked Questions

When is the project scheduled to finish?

Construction is scheduled to finish in December 2026. The work started in June 2026. TDLR completed plan review in July 2026. The total build window is 193 days.

What is the scope of the renovation?

The scope includes interior renovation of 38,000 square feet on the sixth floor. It involves new staff offices and student group study support spaces at Alkek Library.

Who is the design firm?

The Lawrence Group is the design firm of record. Martelle Luedecke is the registered accessibility specialist for the project.

What is the estimated cost?

The estimated cost is $3,500,000. This equates to $92 per square foot. The cost is above the county median for renovation projects.

Is the library open for this project?

The TDLR record covers construction status only. It does not indicate if the library is open. The project is scheduled to finish in December 2026.

What is Texas State University: Student Success Commons at Albert B. Alkek Library building?

Texas State University: Student Success Commons at Albert B. Alkek Library building is a renovation/alteration project at 601 University Drive in San Marcos, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Interior renovation of approx. 38,000 s.f. of the 6th floor of Alkek Library. The work will include new staff offices and student group study support spaces.

Is Texas State University: Student Success Commons at Albert B. Alkek Library building open in San Marcos?

Texas State University: Student Success Commons at Albert B. Alkek Library building is still under construction in San Marcos, TX, with an estimated completion of Dec 2026 according to its TDLR registration.

Where is Texas State University: Student Success Commons at Albert B. Alkek Library building located?

Texas State University: Student Success Commons at Albert B. Alkek Library building is located at 601 University Drive, San Marcos, TX, 78666, in Hays County.

Who is the owner or developer of Texas State University: Student Success Commons at Albert B. Alkek Library building?

Texas State University is the property owner/developer of record for Texas State University: Student Success Commons at Albert B. Alkek Library building, per its TDLR project registration.

Who is the architect or design firm for Texas State University: Student Success Commons at Albert B. Alkek Library building?

Lawrence Group is the design firm of record for Texas State University: Student Success Commons at Albert B. Alkek Library building, according to its TDLR filing.

How much does Texas State University: Student Success Commons at Albert B. Alkek Library building cost and how big is it?

Texas State University: Student Success Commons at Albert B. Alkek Library building has an estimated construction value of $3.5M and approximately 38,000 square feet (about $92/sqft), based on its TDLR filing.

Scope of Work

Interior renovation of approx. 38,000 s.f. of the 6th floor of Alkek Library. The work will include new staff offices and student group study support spaces.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

601 University Drive, San Marcos, TX, 78666

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Related City Permits

Building permits found at or near this location

601 W ST JOHNS AVE UNIT 2324

Replacement of complete existing central heat and air system with or without duct work

ActiveMechanical PermitChange OutNov 2026
View Details
2026-143439 MP
Texas Multifamily Solution, LLC
601 W 2ND ST BLDG FLR18

Tenant improvement of shell office space and minor renovations of existing shell amenity storage and mechanical spaces. Work to include stairwell only work to Floors 19-20.

ActivePlumbing PermitRemodelNov 2026
View Details
2026-138811 PP
Mechanical & Process Systems
601 W 2ND ST BLDG FLR18

Tenant improvement of shell office space and minor renovations of existing shell amenity storage and mechanical spaces. Work to include stairwell only work to Floors 19-20.

ActiveMechanical PermitRemodelNov 2026
View Details
2026-138811 MP
Mechanical & Process Systems, Llc
601 W 2ND ST BLDG FLR17

Tenant improvement of shell office space and minor renovations of existing shell amenity storage and mechanical spaces. Work to include stairwell only work to Floors 19-20.

ActiveMechanical PermitRemodelNov 2026
View Details
2026-138810 MP
Mechanical & Process Systems, Llc
601 W 2ND ST BLDG FLR17

Tenant improvement of shell office space and minor renovations of existing shell amenity storage and mechanical spaces. Work to include stairwell only work to Floors 19-20.

ActivePlumbing PermitRemodelNov 2026
View Details
2026-138810 PP
Mechanical & Process Systems

Watch all construction in 78666 (San Marcos)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in San Marcos?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.