Project intelligenceTDLR TABS2026028426New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

FM 1112 (CSJ: 1283-01-012) in Marfa, TX

From: 1/2 Block W of Highland Street To: B Street, Marfa, TX, 79843

Opening ~Oct 2027Review Complete

FM 1112 (CSJ: 1283-01-012) is a new construction project at From: 1/2 Block W of Highland Street To: B Street, Marfa, in Presidio County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Oct 2027. The project has an estimated value of $1.3M across about 5,601 sq ft.

Estimated project value
$1.3M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
5,601 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$229/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
4 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Aug 20, 2026413 days across supplied datesOct 7, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    7 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    278 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    128 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About FM 1112 (CSJ: 1283-01-012)

TxDOT District: El Paso is constructing a new pedestrian bridge, sidewalks, and a shared-use path in Marfa, Texas. The project, filed under the name FM 1112 (Csj: 1283-01-012), covers a route from one-half block west of Highland Street to B Street. This new construction effort spans 5,601 sq ft and is estimated to cost $1,281,294.

The work is scheduled to finish in October 2027, with construction starting in June 2027. TDLR completed plan review in August 2026, clearing the path for this infrastructure upgrade. The project involves public funds and is located on public land, ensuring it serves the broader community of Presidio County.

Project Scope and Cost

The scope of work includes the construction of sidewalks, pedestrian ramps, a shared use path, and the pedestrian bridge itself. At $229 per square foot, the cost is close to the county median of $201 for similar new construction filings. The total estimated cost of $1,281,294 is also close to the Presidio County median of $1,425,900 for comparable projects.

TxDOT District: El Paso is responsible for six other TDLR-registered projects in the region, with a combined value exceeding $100 million. This Marfa project fits within that broader portfolio of infrastructure development. The estimated build window of 128 days is shorter than the county median of 310 days for similar new construction filings.

Local Context

Marfa is a small community with a population of about 2,578 according to U.S. Census estimates for ZIP code 79843. The median household income in the area is $39,423, and the median owner-occupied home value is $228,300. Housing in the area is predominantly owner-occupied, with 1,639 housing units recorded.

Presidio County has an unemployment rate of 6.7 percent according to FRED data. The project’s registration with TDLR was finalized in August 2026, and the status is Review Complete. This ensures compliance with accessibility standards before construction begins in mid-2027.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79843 (Marfa)

One email per change. Unsubscribe in one click. Privacy.

FM 1112 (CSJ: 1283-01-012) is a New Construction project located at From: 1/2 Block W of Highland Street To: B Street, Marfa, TX 79843 in Marfa, Texas. The project has an estimated value of $1.3M covering 5,601 sq ft. TxDOT District: El Paso is the property owner. The project was registered with TDLR on August 20, 2026.

Frequently Asked Questions

When is the Marfa pedestrian bridge project scheduled to finish?

The project is scheduled to finish in October 2027, with construction starting in June 2027. Plan review was completed in August 2026.

What is the estimated cost of the FM 1112 project in Marfa?

The estimated cost is $1,281,294. This figure is close to the Presidio County median for similar new construction projects.

Who is the owner of record for this Marfa construction project?

The owner of record is TxDOT District: El Paso. The project involves public funds and is located on public land.

What specific infrastructure is included in the scope of work?

The scope includes construction of sidewalks, pedestrian ramps, a shared use path, and a pedestrian bridge. The total area is 5,601 sq ft.

Is the pedestrian bridge in Marfa open to the public?

The project is under construction and scheduled to finish in October 2027. It is not yet open to the public.

What is FM 1112 (CSJ: 1283-01-012)?

FM 1112 (CSJ: 1283-01-012) is a new construction project at From: 1/2 Block W of Highland Street To: B Street in Marfa, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construction of sidewalks, pedestrian ramps, shared use path and pedestrian bridge.

Is FM 1112 (CSJ: 1283-01-012) open in Marfa?

FM 1112 (CSJ: 1283-01-012) is still under construction in Marfa, TX, with an estimated completion of Oct 2027 according to its TDLR registration.

Where is FM 1112 (CSJ: 1283-01-012) located?

FM 1112 (CSJ: 1283-01-012) is located at From: 1/2 Block W of Highland Street To: B Street, Marfa, TX, 79843, in Presidio County.

Who is the owner or developer of FM 1112 (CSJ: 1283-01-012)?

TxDOT District: El Paso is the property owner/developer of record for FM 1112 (CSJ: 1283-01-012), per its TDLR project registration.

How much does FM 1112 (CSJ: 1283-01-012) cost and how big is it?

FM 1112 (CSJ: 1283-01-012) has an estimated construction value of $1.3M and approximately 5,601 square feet (about $229/sqft), based on its TDLR filing.

Scope of Work

Construction of sidewalks, pedestrian ramps, shared use path and pedestrian bridge.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

From: 1/2 Block W of Highland Street To: B Street, Marfa, TX, 79843

Loading location map…
30.31446, -104.01229

Watch all construction in 79843 (Marfa)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.