Project intelligenceTDLR TABS2026028451Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road

Mockingbird Lane - From N Midlothian Parkway to N, Midlothian, TX, 76065

Opening ~Jan 2029Review Complete

Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road is a renovation/alteration project at Mockingbird Lane - From N Midlothian Parkway to N, Midlothian, in Ellis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Jan 2029. The project has an estimated value of $999.0M across about 73,000 sq ft.

Estimated project value
$999.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
73,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$13.68K/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2 years
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Aug 21, 2026864 days across supplied datesJan 1, 2029

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    19 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    114 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    731 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road

The City of Midlothian is leading a major roadway renovation on Mockingbird Lane, spanning the stretch from N Midlothian Parkway to N Walnut Grove Road in Midlothian, Texas. This project involves the widening of the roadway and the reconstruction of three intersections, transforming a two-lane asphalt road into a two-to-four-lane concrete surface with monolithic curb and gutter. The estimated cost for this infrastructure upgrade is $999,000,000, covering a site area of 73,000 square feet.

Project Scope and Design

Kimley-Horn and Associates, Inc. serves as the design firm of record for this complex renovation. The scope of work includes replacing the existing asphalt with 8-inch thick concrete, ensuring a durable surface for the expanded lane configuration. This project is registered with the Texas Department of Licensing and Regulation (TDLR) under the accessibility program, with Ross A Thomas listed as the registered accessibility specialist. The filing indicates that the project involves public funds and public land, characterizing it as a Federally funded roadway project.

TDLR completed the plan review process in September 2026, clearing the path for construction to begin in January 2027. The construction timeline is scheduled to finish in January 2029, representing a two-year build window. This duration is significantly longer than the median 92-day build window for similar renovation and alteration filings in Ellis County. The estimated cost per square foot is $13,685, which is above the county median of $84 for comparable projects.

Local Context and Funding

The City of Midlothian has six other TDLR-registered projects totaling $26,749,000, including recent sidewalk programs and road improvements on Mt. Zion Road and Hawkins Run Road. Kimley-Horn and Associates, Inc. has also been the design firm for six other registered projects, such as the Trinity Gardens Park in Houston. The project site is located in ZIP code 76065, where the U.S. Census Bureau estimates a population of approximately 44,614 and a median household income of $123,664. The area is predominantly owner-occupied, with a median home value of $378,600.

Third-party bid notices from ConstructConnect and CivCast confirm the project's listing with a bid date of September 15, 2026. The Ellis County unemployment rate was 4.5 percent in July 2026, higher than a year earlier, providing context for the local labor market during this construction period.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76065 (Midlothian)

One email per change. Unsubscribe in one click. Privacy.

Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road is a Renovation/Alteration project located at Mockingbird Lane - From N Midlothian Parkway to N, Midlothian, TX 76065 in Midlothian, Texas. The project has an estimated value of $999.0M covering 73,000 sq ft. City of Midlothian is the property owner and Kimley-Horn and Associates, Inc. is the design firm of record. The project was registered with TDLR on August 21, 2026.

Frequently Asked Questions

When is the Mockingbird Lane renovation scheduled to finish?

Construction is scheduled to finish in January 2029. Work is set to start in January 2027, following the completion of TDLR plan review in September 2026.

Who is the owner of the Mockingbird Lane project?

The City of Midlothian is the owner and developer of record. Kimley-Horn and Associates, Inc. is the design firm of record for the project.

What is the estimated cost of this roadway project?

The estimated cost is $999,000,000. This figure covers the widening of Mockingbird Lane and the reconstruction of three intersections in Midlothian.

Is the Mockingbird Lane project open to the public?

The project is a construction site and is not a business open to the public. It is a roadway renovation scheduled to finish in January 2029.

Who is the registered accessibility specialist for this filing?

Ross A Thomas is the registered accessibility specialist of record for this TDLR-registered project in Ellis County.

What is Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road?

Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road is a renovation/alteration project at Mockingbird Lane - From N Midlothian Parkway to N in Midlothian, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Widening of Mockingbird Lane from Midlothian Parkway to Walnut Grove, and reconstruction of 3 intersections. Roadway will be reconstructed from 2 lane asphalt to two to four lane 8" thick concrete with monolithic curb and gutter roadway.

Is Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road open in Midlothian?

Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road is still under construction in Midlothian, TX, with an estimated completion of Jan 2029 according to its TDLR registration.

Where is Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road located?

Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road is located at Mockingbird Lane - From N Midlothian Parkway to N, Midlothian, TX, 76065, in Ellis County.

Who is the owner or developer of Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road?

City of Midlothian is the property owner/developer of record for Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road, per its TDLR project registration.

Who is the architect or design firm for Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road?

Kimley-Horn and Associates, Inc. is the design firm of record for Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road, according to its TDLR filing.

How much does Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road cost and how big is it?

Mockingbird Lane - From N Midlothian Parkway to N Walnut Grove Road has an estimated construction value of $999.0M and approximately 73,000 square feet (about $13.68K/sqft), based on its TDLR filing.

Scope of Work

Widening of Mockingbird Lane from Midlothian Parkway to Walnut Grove, and reconstruction of 3 intersections. Roadway will be reconstructed from 2 lane asphalt to two to four lane 8" thick concrete with monolithic curb and gutter roadway.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Mockingbird Lane - From N Midlothian Parkway to N, Midlothian, TX, 76065

Loading location map…
32.49112, -96.97628

Watch all construction in 76065 (Midlothian)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Midlothian?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.