Project intelligenceTDLR TABS2026028528New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

MVISD Elementary School #7 in San Antonio, TX

7750 Blacktail Crest, San Antonio, TX, 78253

Opening ~May 2028Review Complete

MVISD Elementary School #7 is a new construction project at 7750 Blacktail Crest, San Antonio, in Bexar County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion May 2028. The project has an estimated value of $47.5M across about 100,750 sq ft.

Estimated project value
$47.5M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
100,750 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$471/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 7mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Aug 21, 2026630 days across supplied datesMay 12, 2028

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    39 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    34 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    557 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About MVISD Elementary School #7

MVISD Elementary School #7 is a new construction project for a PK-5th grade facility located at 7750 Blacktail Crest in San Antonio. The building spans 100,750 square feet with an estimated cost of $47,500,000. The project is registered with TDLR, and completion is targeted for May 2028.

The owner of record is Medina Valley Independent School District, which is developing the site on public land. Alamo Architects serves as the design firm of record for this new educational facility. The registered accessibility specialist is Asa Joel Meyer. The filing indicates the project involves public funds and public land.

Project Scale and Cost

The estimated cost of $47,500,000 places this project above the median estimated cost for new construction filings in Bexar County. The median cost for comparable projects in the county is $600,000. The size of 100,750 square feet is significantly larger than the median size of 6,300 square feet for new construction in the area. The cost per square foot is $471, which is above the county median of $115 per square foot.

The scheduled build window is 557 days, which is longer than the median scheduled build window of 208 days for new construction projects in Bexar County. Construction is set to begin in November 2026. The project was registered with TDLR in August 2026. Plan review is pending.

Context and Area Profile

Medina Valley Independent School District has five other TDLR-registered projects totaling $46,995,000. These include Ladera Elementary School, Potranco Elementary School, Silos Elementary School, MVISD Luckey Ranch Elementary School, and Medina Valley High School Addition #2. Alamo Architects has six other TDLR-registered projects totaling $23,547,171, all with review complete status.

The site is located in ZIP code 78253, which has a population of about 67,578 according to U.S. Census ACS 2023 five-year estimates. The median household income in this area is $104,260. Bexar County unemployment rate was 4.7 percent in July 2026, higher than a year earlier.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78253 (San Antonio)

One email per change. Unsubscribe in one click. Privacy.

MVISD Elementary School #7 is a New Construction project located at 7750 Blacktail Crest, San Antonio, TX 78253 in San Antonio, Texas. The project has an estimated value of $47.5M covering 100,750 sq ft. Medina Valley Independent School District is the property owner and Alamo Architects is the design firm of record. The project was registered with TDLR on August 21, 2026.

Frequently Asked Questions

Is MVISD Elementary School #7 open?

The project is in the construction phase. It is not open. The TDLR record shows the project is registered, plan review is pending, and completion is targeted for May 2028.

Who is building MVISD Elementary School #7?

Medina Valley Independent School District is the owner of record. Alamo Architects is the design firm of record. Asa Joel Meyer is the registered accessibility specialist.

What is the estimated cost of MVISD Elementary School #7?

The estimated cost is $47,500,000. This is above the median estimated cost for new construction filings in Bexar County, which is $600,000.

When will MVISD Elementary School #7 be completed?

Completion is targeted for May 2028. Construction is set to begin in November 2026. The project was registered with TDLR in August 2026.

Where is MVISD Elementary School #7 located?

The project is located at 7750 Blacktail Crest, San Antonio, TX 78253.

What is MVISD Elementary School #7?

MVISD Elementary School #7 is a new construction project at 7750 Blacktail Crest in San Antonio, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New Elementary School for PK-5th grade students.

Is MVISD Elementary School #7 open in San Antonio?

MVISD Elementary School #7 is still under construction in San Antonio, TX, with an estimated completion of May 2028 according to its TDLR registration.

Who is the owner or developer of MVISD Elementary School #7?

Medina Valley Independent School District is the property owner/developer of record for MVISD Elementary School #7, per its TDLR project registration.

Who is the architect or design firm for MVISD Elementary School #7?

Alamo Architects is the design firm of record for MVISD Elementary School #7, according to its TDLR filing.

How much does MVISD Elementary School #7 cost and how big is it?

MVISD Elementary School #7 has an estimated construction value of $47.5M and approximately 100,750 square feet (about $471/sqft), based on its TDLR filing.

Scope of Work

New Elementary School for PK-5th grade students.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

7750 Blacktail Crest, San Antonio, TX, 78253

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 78253 (San Antonio)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in San Antonio?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.