Approved and ReleasedDistrict 2
Easton Park Segment D, 16" Water Transmission Main
The applicant is proposing to revise a previously approved site plan.
9621-1/2 APOGEE BLVD, AUSTIN, TX, 78744 Site Plan AUSTIN LTD
Entitled100%
Timeline
Applied: Mar 14, 2025
Updated: Dec 22, 2025
Site Plan Metrics
#13484387ABC Portal β
Work Type
Utility Line
Sub Type
Site Plan Administrative
Approved and Released
Step 5 of 5: Released βSite plan fully approved and released. All conditions cleared. Ready for construction permitting.
Next:Pull building permits to begin construction.
Scope of Work
The applicant is proposing to revise a previously approved site plan.
Entitlement Timeline
Application Filed
+30dMarch 14, 2025
In Review
+255dApril 13, 2025
Approved
December 23, 2025
π€ Project Contacts
2 peopleRoles reflect the company these contacts represent on this project.
π Owner Contact
βοΈEngineer ContactπApplicant Contact
Related Case
View Related Site Plan β
Folder RSN: Yes
Fees
UDS Engineering Plan Review Update
$620.06
OutstandingUDS Engineering Plan Review
$120.50
OutstandingUtility & Storm Sewers-DSD
$3,043.15
OutstandingAE - Site Plan Review
$262.00
OutstandingAE-Technology Fee
$26.20
OutstandingTechnology Surcharge-DSD
$182.59
OutstandingPARD-Site Plan/Subdivision Review Fee
$916.02
OutstandingFIRE-Fire Site Plan Review
$340.00
OutstandingCompleteness Check Fee
$401.90
OutstandingWPD-Site Plan Completeness Check
$34.00
OutstandingTechnology Surcharge-DSD
$26.15
OutstandingNearby Site Plans
South Austin RV Park
Expired β’ AUSTIN β’ Jan 21, 2022
South Austin RV Park
Aborted β’ AUSTIN β’ Mar 13, 2020
Caswell Services, Inc.
Expired β’ AUSTIN β’ Mar 28, 2016
Coulver Rd-Dry Creek Ranch
Expired β’ AUSTIN β’ Mar 26, 2024
Dry Creek-AWU-Extension
Withdrawn β’ AUSTIN β’ Mar 15, 2024
Dry Creek-AWU-Extension Line A
Approved and Released β’ AUSTIN β’ Dec 16, 2025
Dry Creek-AWU-Extension Line B
Approved and Released β’ AUSTIN β’ Dec 16, 2025
Schmidt Electric
Expired β’ AUSTIN β’ Aug 25, 2017
Easton Park South-South Fork Lift Station and Force Main
Approved and Released β’ AUSTIN β’ Aug 26, 2025
THAXTON AUSTX
Expired β’ AUSTIN β’ Jul 13, 2025
Easton Park Construction Spoils Storage Site Plan
Approved and Released β’ AUSTIN β’ Jul 11, 2025
Easton Park Town Center Site A
Awaiting Update β’ AUSTIN β’ Jul 7, 2026
Key Stakeholders
Zoning & Land Use
Current Zoning
PUD - PLANNED UNIT DEVELOPMENT
Existing Use
Horizontal Infrastructure
Proposed Use
Horizontal Infrastructure
Environmental & Geographic
Watershed ClassSuburban Watershed
School DistrictDEL VALLE ISD
Case Manager
Jennifer Bennett
City of Austin Development Services
Explore Area
Case Details
Case Number13484387
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-2022-0317D(R1)
JurisdictionAUSTIN LTD
Property RSN6483038