METRO BURNETT STREET IMPROVEMENTS

800 BURNETT STREET, Houston, TX 77009, Houston, TX, 77009
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4807006
$250K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 2mo
Duration
Registered:Jan 6, 2014
Start:May 1, 2014
Target:Jun 30, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construct concrete curb and gutter roadway with utilityrelocation, storm sewer, sidewalk, pedestrian ramps, and

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 6, 2014
Construction Start
May 1, 2014
Expected Completion