πProject ClosedποΈ New Construction
Alpine Area Engineer and Maintenance Facility
Completed100%
πProject Metrics
TDLR #TABS2021005342$7.3M
Project Value
β
Square Feet
β
Cost/SqFt
1 year
Duration
Registered:Dec 3, 2020
Start:Jan 10, 2021
Target:Jan 8, 2022
π
Project Closed
Project has been completed and closed
π Compliance Timeline
Project Registered
December 3, 2020
Construction Start
January 10, 2021
Expected Completion
January 8, 2022