Construction complete ยท Aug 2022๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Complete Streets Phase I

Intersection of Broad St and Cedar St, Cedar Hill, TX 75104, Cedar Hill, TX, 75104

Complete Streets Phase I is a renovation/alteration project at Intersection of Broad St and Cedar St, Cedar Hill, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Aug 2022). The project has an estimated value of $300K across about 14,000 sq ft.

Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022003454
$300K
Project Value
14,000
Square Feet
$21/sqft
Cost/SqFt
8 months
Duration
Registered:Oct 19, 2021
Start:Jan 1, 2022
Target:Aug 31, 2022
๐Ÿ

Project Closed

Project has been completed and closed

Complete Streets Phase I is a Renovation/Alteration project located at Intersection of Broad St and Cedar St, Cedar Hill, TX 75104 in Cedar Hill, Texas. The project has an estimated value of $300K covering 14,000 sq ft. City of Cedar Hill is the property owner and Pacheco Koch Consulting Engineers, Inc. is the design firm of record. The project was registered with TDLR on October 19, 2021.

โ“Frequently Asked Questions

What is Complete Streets Phase I?

Complete Streets Phase I is a renovation/alteration project at Intersection of Broad St and Cedar St in Cedar Hill, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: The project is a complete street reconstruction of Broad Street from Belt Line Road to Cedar Street and Cedar Street from Broad Street to the BNSF railroad ROW in downtown Cedar Hill.

Is Complete Streets Phase I open in Cedar Hill?

Construction on Complete Streets Phase I is complete โ€” TDLR records show the project passed its required accessibility inspection in Aug 2022. The building is finished and very likely open.

Where is Complete Streets Phase I located?

Complete Streets Phase I is located at Intersection of Broad St and Cedar St, Cedar Hill, TX, 75104, in Dallas County.

Who is the owner or developer of Complete Streets Phase I?

City of Cedar Hill is the property owner/developer of record for Complete Streets Phase I, per its TDLR project registration.

Who is the architect or design firm for Complete Streets Phase I?

Pacheco Koch Consulting Engineers, Inc. is the design firm of record for Complete Streets Phase I, according to its TDLR filing.

How much does Complete Streets Phase I cost and how big is it?

Complete Streets Phase I has an estimated construction value of $300K and approximately 14,000 square feet (about $21/sqft), based on its TDLR filing.

๐Ÿ“‹Scope of Work

The project is a complete street reconstruction of Broad Street from Belt Line Road to Cedar Street and Cedar Street from Broad Street to the BNSF railroad ROW in downtown Cedar Hill.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 19, 2021
Project Closed
August 31, 2022
Construction Start
January 1, 2022
Expected Completion
August 31, 2022

๐Ÿ“…Project Timeline

Filed

Oct 19, 2021

Review Complete

Inspection Complete

Closed

Aug 31, 2022

Get alerts for Dallas

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists