๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Timber Creek Trail Segment F
Intersection of Misty Lane and Andrea Court, Lewisville, TX 75067, Lewisville, TX, 75067
Construction50%
๐Project Metrics
TDLR #TABS2024007802$3.0M
Project Value
140,000
Square Feet
$21/sqft
Cost/SqFt
2y 1mo
Duration
Registered:Dec 19, 2023
Start:Jun 1, 2024
Target:Jul 1, 2026
Remaining:186 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Public Trail and sidewalk, 140,000 sf
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 19, 2023
Construction Start
June 1, 2024
Expected Completion
July 1, 2026
๐Related Projects
๐คSame Owner
$3.8M totalProperty Owner
๐ค
CITY OF LEWISVILLE TX
Contact: Randy Simon
4 projects ยท $3.8M
View company profile
191 Civic Circle, Lewisville, Texas 75067
Design Firm
๐๏ธ
TBG Partners
4 projects ยท $12.0M
View all projects
2001 Bryan Street, Suite 1450, Dallas, Texas 75201