BP PULSE EV CHARGING STATIONS 426

100 HOPKINS RD, Sweetwater, TX, 79556

Target date passed (Sep 2024)Review Complete

BP PULSE EV CHARGING STATIONS 426 is a renovation/alteration project at 100 HOPKINS RD, Sweetwater, in Nolan County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Sep 2024 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $175K across about 500 sq ft.

Estimated project value
$175K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
500 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$350/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Mar 20, 2024181 days across supplied datesSep 17, 2024

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    139 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    42 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79556 (Sweetwater)

One email per change. Unsubscribe in one click. Privacy.

BP PULSE EV CHARGING STATIONS 426 is a Renovation/Alteration project located at 100 HOPKINS RD, Sweetwater, TX 79556 in Sweetwater, Texas. The project has an estimated value of $175K covering 500 sq ft. TA OPERATING LLC is the property owner and LDC CORP is the design firm of record. The project was registered with TDLR on March 20, 2024.

Frequently Asked Questions

What is BP PULSE EV CHARGING STATIONS 426?

BP PULSE EV CHARGING STATIONS 426 is a renovation/alteration project at 100 HOPKINS RD in Sweetwater, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: INSTALL 6 LEVEL 3 ELECTRIC VEHICLE CHARGING STATIONS IN EXISTING PARKING LOT

Is BP PULSE EV CHARGING STATIONS 426 open in Sweetwater?

BP PULSE EV CHARGING STATIONS 426 was scheduled to finish construction in Sep 2024 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is BP PULSE EV CHARGING STATIONS 426 located?

BP PULSE EV CHARGING STATIONS 426 is located at 100 HOPKINS RD, Sweetwater, TX, 79556, in Nolan County.

Who is the owner or developer of BP PULSE EV CHARGING STATIONS 426?

TA OPERATING LLC is the property owner/developer of record for BP PULSE EV CHARGING STATIONS 426, per its TDLR project registration.

Who is the architect or design firm for BP PULSE EV CHARGING STATIONS 426?

LDC CORP is the design firm of record for BP PULSE EV CHARGING STATIONS 426, according to its TDLR filing.

How much does BP PULSE EV CHARGING STATIONS 426 cost and how big is it?

BP PULSE EV CHARGING STATIONS 426 has an estimated construction value of $175K and approximately 500 square feet (about $350/sqft), based on its TDLR filing.

Scope of Work

INSTALL 6 LEVEL 3 ELECTRIC VEHICLE CHARGING STATIONS IN EXISTING PARKING LOT

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

100 HOPKINS RD, Sweetwater, TX, 79556

Location by street address

Watch all construction in 79556 (Sweetwater)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Sweetwater?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.