Project intelligenceTDLR TABS2024023059Additions to Existing Building
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Goliad Elementary School Gym Addition

142 W High Street, Goliad, TX, 77963

Construction complete · Jul 2025Inspection Complete

Goliad Elementary School Gym Addition is a additions to existing building project at 142 W High Street, Goliad, in Goliad County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jul 2025). The project has an estimated value of $3.5M across about 9,600 sq ft.

Estimated project value
$3.5M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
9,600 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$365/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
9 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jul 15, 2024374 days across supplied datesJul 24, 2025

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    112 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    262 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77963 (Goliad)

One email per change. Unsubscribe in one click. Privacy.

Goliad Elementary School Gym Addition is a Additions to Existing Building project located at 142 W High Street, Goliad, TX 77963 in Goliad, Texas. The project has an estimated value of $3.5M covering 9,600 sq ft. Goliad Independent School District is the property owner and BWA Architects is the design firm of record. The project was registered with TDLR on July 15, 2024.

Frequently Asked Questions

What is Goliad Elementary School Gym Addition?

Goliad Elementary School Gym Addition is a additions to existing building project at 142 W High Street in Goliad, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New Gym Addition to existing Elementary School

Is Goliad Elementary School Gym Addition open in Goliad?

Construction on Goliad Elementary School Gym Addition is complete — TDLR records show the project passed its required accessibility inspection in Jul 2025. The building is finished and very likely open.

Where is Goliad Elementary School Gym Addition located?

Goliad Elementary School Gym Addition is located at 142 W High Street, Goliad, TX, 77963, in Goliad County.

Who is the owner or developer of Goliad Elementary School Gym Addition?

Goliad Independent School District is the property owner/developer of record for Goliad Elementary School Gym Addition, per its TDLR project registration.

Who is the architect or design firm for Goliad Elementary School Gym Addition?

BWA Architects is the design firm of record for Goliad Elementary School Gym Addition, according to its TDLR filing.

How much does Goliad Elementary School Gym Addition cost and how big is it?

Goliad Elementary School Gym Addition has an estimated construction value of $3.5M and approximately 9,600 square feet (about $365/sqft), based on its TDLR filing.

Scope of Work

New Gym Addition to existing Elementary School

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

142 W High Street, Goliad, TX, 77963

Loading location map…
28.67064, -97.39314

Watch all construction in 77963 (Goliad)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.