๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Sherman Multi-Purpose Stadium
2907 W. TRAVIS AT W. MOORE, Sherman, TX 75092, Sherman, TX, 75092
Construction50%
๐Project Metrics
TDLR #TABS2024026699$40.0M
Project Value
130,716
Square Feet
$306/sqft
Cost/SqFt
1y 5mo
Duration
Registered:Aug 30, 2024
Start:Oct 21, 2024
Target:Mar 16, 2026
Remaining:80 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New press box, grandstand, concourse building including concession and group restroom. New visitor locker building. New parking lot.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 30, 2024
Construction Start
October 21, 2024
Expected Completion
March 16, 2026
๐Related Projects
๐คSame Owner
$187.6M totalProperty Owner
๐ค
SHERMAN ISD
4 projects ยท $187.6M
View company profile
2701 N Loy Lake Rd, Sherman, Texas 75090
Design Firm
๐๏ธ
VLK ARCHITECTS
4 projects ยท $105.0M
View company profile
1320 Hemphill St, Suite 400, Fort Worth, Texas 76104