Project intelligenceTDLR TABS2025003646Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Strickland Middle School Track & Field Renovation in Denton, TX

3003 N Bell Ave, Denton, TX, 76209

Target date passed (Mar 2025)Project Registered

Strickland Middle School Track & Field Renovation is a renovation/alteration project at 3003 N Bell Ave, Denton, in Denton County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Mar 2025 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $4.0M across about 2,400 sq ft.

Estimated project value
$4.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
2,400 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$1.67K/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
5 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 21, 2024158 days across supplied datesMar 28, 2025

3 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    22 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    136 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Strickland Middle School Track & Field Renovation

The Strickland Middle School Track & Field Renovation at 3003 N Bell Ave in Denton involves a new 2,400 sq ft athletics storage building and significant upgrades to the school’s sports facilities. The project, registered with TDLR in October 2024, carries an estimated cost of $4,000,000 and was scheduled for completion by March 2025. The scope includes adding artificial turf to the existing football field, renovating the track, creating new event areas, and installing additional chain link fencing around the athletics zone.

Scope and Design

Corgan Associates, Inc. serves as the design firm of record for this renovation and alteration project. The work is not limited to the new storage structure; it comprehensively updates the outdoor athletic environment. By adding artificial turf and renovating the track, the district aims to improve the durability and usability of the sports fields. The inclusion of new track and field event areas suggests an expansion of the types of competitions or practices the facility can host. Additional chain link fencing is planned to secure the athletics area, a common requirement for maintaining safety and controlling access to high-traffic school zones.

The estimated cost of $4,000,000 places this project above the median estimated cost for renovation and alteration filings in Denton County. The median for similar projects in the county is $237,622, with the middle half falling between $125,000 and $551,594. This project’s cost per square foot is $1,667, which is significantly above the county median of $81 per square foot. The scheduled build window of 136 days is also longer than the county median of 92 days, reflecting the complexity of coordinating structural construction with outdoor field renovations.

Project Status and Record

The project was registered with TDLR in October 2024 with a target completion of March 2025; no plan review or inspection has been recorded since, so whether it proceeded is not confirmed in the public record. Denton Independent School District is the owner of record and has six other TDLR-registered projects totaling $22,255,801, including renovations at Pecan Creek Elementary School and McMath Middle School. Corgan Associates, Inc. has been involved in other high-profile projects, such as work at DFW Airport, indicating a design firm with experience in large-scale commercial and institutional developments.

The project involves public funds and public land, consistent with its status as a school district facility. The address is located in Denton County, where the unemployment rate was 4.2 percent in August 2026. The surrounding area, ZIP code 76209, has a population of about 27,859 and a median household income of $66,883. Housing in this ZIP code is mostly renter-occupied, with a median owner-occupied home value of $248,900. These demographic details provide context for the community served by Strickland Middle School and the local economic environment in which this construction took place.

Project Registered

Project has been registered with TDLR and is in pre-construction phase

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76209 (Denton)

One email per change. Unsubscribe in one click. Privacy.

Strickland Middle School Track & Field Renovation is a Renovation/Alteration project located at 3003 N Bell Ave, Denton, TX 76209 in Denton, Texas. The project has an estimated value of $4.0M covering 2,400 sq ft. Denton Independent School District is the property owner and Corgan Associates, Inc. is the design firm of record. The project was registered with TDLR on October 21, 2024.

Frequently Asked Questions

What is the estimated cost of the Strickland Middle School renovation?

The estimated cost for the Strickland Middle School Track & Field Renovation is $4,000,000. This figure covers the new 2,400 sq ft storage building, turf installation, track renovation, and fencing.

Who is the design firm for this project?

Corgan Associates, Inc. is the design firm of record for the Strickland Middle School renovation. They are responsible for the architectural and design aspects of the athletics upgrades.

Is the project complete?

The filing listed a completion date of March 2025. However, no plan review or inspection has been recorded since registration, so completion is not confirmed in the public record.

What new structures are being built?

The project includes a new 2,400 sq ft athletics storage building. It also involves renovating the existing track and adding artificial turf to the football field.

Which school district owns the facility?

Denton Independent School District is the owner of record for the Strickland Middle School Track & Field Renovation project located at 3003 N Bell Ave.

What is Strickland Middle School Track & Field Renovation?

Strickland Middle School Track & Field Renovation is a renovation/alteration project at 3003 N Bell Ave in Denton, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New 2,400 sq ft athletics storage building. Artificial turf added to existing football field. Renovated track around field. New track & field event areas. Additional chain link fence around athletics.

Is Strickland Middle School Track & Field Renovation open in Denton?

Strickland Middle School Track & Field Renovation was scheduled to finish construction in Mar 2025 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is Strickland Middle School Track & Field Renovation located?

Strickland Middle School Track & Field Renovation is located at 3003 N Bell Ave, Denton, TX, 76209, in Denton County.

Who is the owner or developer of Strickland Middle School Track & Field Renovation?

Denton Independent School District is the property owner/developer of record for Strickland Middle School Track & Field Renovation, per its TDLR project registration.

Who is the architect or design firm for Strickland Middle School Track & Field Renovation?

Corgan Associates, Inc. is the design firm of record for Strickland Middle School Track & Field Renovation, according to its TDLR filing.

How much does Strickland Middle School Track & Field Renovation cost and how big is it?

Strickland Middle School Track & Field Renovation has an estimated construction value of $4.0M and approximately 2,400 square feet (about $1.67K/sqft), based on its TDLR filing.

Scope of Work

New 2,400 sq ft athletics storage building. Artificial turf added to existing football field. Renovated track around field. New track & field event areas. Additional chain link fence around athletics.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

3003 N Bell Ave, Denton, TX, 76209

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 76209 (Denton)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.