๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
FM 3391 (CSJ: 3372-01-010)
From: IH 35W TO: East of CR 602, Burleson, TX 76028, Burleson, TX, 76028
Construction50%
๐Project Metrics
TDLR #TABS2025005578$80.6M
Project Value
201,653
Square Feet
$400/sqft
Cost/SqFt
2y 5mo
Duration
Registered:Nov 14, 2024
Start:Feb 4, 2028
Target:Jun 18, 2030
Remaining:1635 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
2.83 miles on FM 3391 widening IH 35 W to S. Hurst Ave. from 2 to 6 lanes and from S. Hurst Ave. to CR 602 widen from 2 to 4 lanes.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 14, 2024
Construction Start
February 4, 2028
Expected Completion
June 18, 2030
๐Related Projects
๐คSame Owner
$74.5M totalProperty Owner
๐ค
TxDOT District: Fort Worth
Contact: Jennifer Carpenter, P.E.
4 projects ยท $74.5M
View company profile
2501 S W Loop 820, Fort Worth, Texas 76133
Design Firm
๐๏ธ
Kimley-Horn
4 projects ยท $40.0M
View all projects
2600 N Central Expressway, Suite 400, Richardson, Texas 75080